18910 W SYLVAN ST 91335

Certificate Information: 18910 W SYLVAN ST 91335

Application / Permit
21010-20000-01525
Plan Check / Job No.
B21VN03765
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 27' x 33'-8" (2) STORY ACCESSORY DWELLING UNIT WITH ROOF DECK PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 10/15/2021
Issuing Office
Current Status
CofO Issued on 3/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 SELLA BENYAMIN
Corrections Issued 5/3/2021 SELLA BENYAMIN
Quality Review Completed 5/5/2021 STEVEN KIM
Plan Check Approved 9/28/2021 SELLA BENYAMIN
Issued 10/15/2021 APPLICANT
CofO in Progress 3/23/2023 JON MCHUGH
Permit Finaled 3/28/2023 JOHN JANSON
CofO Issued 3/28/2023 JOHN JANSON
Permit Finaled 3/28/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/10/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 5/10/2021 GABRIEL ROBLES
Sewer availability Cleared 5/10/2021 GABRIEL ROBLES
Construction near power lines Cleared 6/14/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 6/28/2021 KURT CORRAL
Low Impact Development Cleared 9/7/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 9/7/2021 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Chatsky,, German; Lic. No.: C84153 6541 ODESSA AVE UNIT 11      LAKE BALBOA, CA 91406

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/4/2021 Approved SEAN HAUPT
Underground Mechanical 12/8/2021 Approved SEAN HAUPT
ELECTRICAL-Rough 1/5/2022 Partial Approval SEAN HAUPT
Footing/Foundation/Slab 1/5/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 2/22/2022 Corrections Issued SEAN HAUPT
Wood Frame 2/28/2022 Approved SEAN HAUPT
ELECTRICAL-Rough 5/2/2022 Approved SEAN HAUPT
HVAC-Rough 5/2/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 5/2/2022 Partial Approval SEAN HAUPT
PLUMBING-Rough 5/2/2022 Approved SEAN HAUPT
Underground Mechanical 5/2/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 5/9/2022 Partial Approval SEAN HAUPT
Interior/Exterior Lathing 5/23/2022 Partial Approval MORRIS JACKSON
Insulation 6/7/2022 Approved MORRIS JACKSON
Drywall Nailing 6/15/2022 Approved SEAN HAUPT
Shower Pan 7/21/2022 Corrections Issued JUSTIN HAWLEY
Shower Pan 7/26/2022 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 8/11/2022 Approved SEAN HAUPT
Sewer 8/23/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 11/15/2022 Approved SEAN HAUPT
ELECTRICAL-Final 11/15/2022 Approved SEAN HAUPT
Final 11/15/2022 Corrections Issued SEAN HAUPT
Green Building Final 11/15/2022 Not Ready for Inspection SEAN HAUPT
Green Building Rough 11/15/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 11/15/2022 SGSOV Approved SEAN HAUPT
Service/Power Release 11/15/2022 Not Ready for Inspection SEAN HAUPT
Smoke Detectors 11/15/2022 Approved SEAN HAUPT
Verify Sprinkler Sign Off 11/15/2022 Approved SEAN HAUPT
Final 2/22/2023 Corrections Issued JON MCHUGH
Green Building Final 2/22/2023 Approved JON MCHUGH
Service/Power Release 2/22/2023 Approved JON MCHUGH
Final 3/8/2023 Partial Approval JON MCHUGH
Final 3/23/2023 OK to Issue CofO JON MCHUGH