6539 N VALJEAN AVE 91406

Certificate Information: 6539 N VALJEAN AVE 91406

Application / Permit
21010-20000-01506
Plan Check / Job No.
B21VN03752
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW (20'-0" x 20'-0"),400 SQFT DETACHED GARAGE
Permit Issued
Issued on 8/5/2022
Issuing Office
Current Status
CofO Issued on 9/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/30/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 PETER MOSESIAN
Corrections Issued 4/4/2021 PETER MOSESIAN
Building Plans Picked Up 4/9/2021 APPLICANT
Issued 8/5/2022 APPLICANT
CofO in Progress 6/18/2025 SALVADOR MARTINEZ
Permit Finaled 9/9/2025 RUBEN SALAS
CofO Issued 9/9/2025 RUBEN SALAS
Permit Finaled 9/9/2025 RUBEN SALAS

Permit Application Clearance Information

ZI Cleared 4/15/2021 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 11/8/2021 ABDULLAH SADOZAI
Low Impact Development Cleared 12/3/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 12/13/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/7/2023 Corrections Issued RAUL OLAGI
Special/Order Compliance 4/7/2023 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 5/4/2023 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 5/23/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 6/15/2023 Approved RAUL OLAGI
ELECTRICAL-Rough 6/15/2023 Approved RAUL OLAGI
Green Building Rough 6/15/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 6/15/2023 Approved RAUL OLAGI
Drywall Nailing 6/27/2023 Approved RAUL OLAGI
Final 5/2/2025 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 5/2/2025 Not Ready for Inspection SALVADOR MARTINEZ
Green Building Final 5/2/2025 Approved SALVADOR MARTINEZ
PLUMBING-Final 5/2/2025 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 5/2/2025 SGSOV Not Ready SALVADOR MARTINEZ
Service/Power Release 5/2/2025 Not Ready for Inspection SALVADOR MARTINEZ
Smoke Detectors 5/2/2025 Approved SALVADOR MARTINEZ
Final 5/29/2025 OK to Issue CofO SALVADOR MARTINEZ
Footing/Foundation/Slab 5/29/2025 Approved SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 5/29/2025 SGSOV Approved SALVADOR MARTINEZ
Service/Power Release 5/29/2025 Approved SALVADOR MARTINEZ