5400 N SHIRLEY AVE 91356
Certificate Information: 5400 N SHIRLEY AVE 91356
- Application / Permit
- 21010-20000-01500
- Plan Check / Job No.
- B21VN03733
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ATTACHED 2-CAR GARAGE.
- Permit Issued
- Issued on 1/30/2023
- Issuing Office
- Valley
- Current Status
- Issued on 1/30/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2021 | HAYATO TSUCHIYA |
| Corrections Issued | 5/4/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 8/31/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 9/1/2021 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 10/18/2021 | APPLICANT |
| Applicant returned to address corrections | 8/29/2022 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 10/21/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 12/27/2022 | RAMA DABADGE |
| Plan Check Approved | 1/9/2023 | JESSE ARELLANO |
| Issued | 1/30/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 4/27/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 8/16/2022 | COLIN LOREDO |
| GPI Written Notices | Cleared | 8/29/2022 | HAYATO TSUCHIYA |
| Grading Pre-Inspection | Cleared | 8/29/2022 | HAYATO TSUCHIYA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vasquez,, Luis Fernando; Lic. No.: C56232 | 1551 RANDALL ST GLENDALE, CA 91201 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/6/2023 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 8/21/2023 | Not Ready for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2023 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 12/26/2023 | Approved | SEAN HAUPT |
| Green Building Rough | 12/26/2023 | Approved | SEAN HAUPT |
| Rough-Elec/Plmb/HVAC | 12/26/2023 | Approved | SEAN HAUPT |
| Drywall Nailing | 3/14/2024 | Approved | JOHN KIDWELL |
| Service/Power Release | 1/9/2025 | Approved | JOHN KIDWELL |
| Final | 12/12/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Final | 12/12/2025 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 12/12/2025 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 12/12/2025 | Approved | JOHN KIDWELL |