6541 N VALJEAN AVE 91406

Certificate Information: 6541 N VALJEAN AVE 91406

Application / Permit
21010-20000-01497
Plan Check / Job No.
B21VN03729
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 51' X 25' 1-STORY 1,200 SQ. FT. ACCESSORY DWELLING UNIT PER LAMC 12.22A33 (c)-(d). NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 7/22/2022
Issuing Office
Current Status
CofO Issued on 9/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/10/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 COLIN LOREDO
Corrections Issued 5/24/2021 COLIN LOREDO
Quality Review Completed 6/4/2021 OMID HEDAYAT
Building Plans Picked Up 6/7/2021 APPLICANT
Plan Check Approved 7/19/2022 COLIN LOREDO
Issued 7/22/2022 APPLICANT
CofO in Progress 6/18/2025 SALVADOR MARTINEZ
Permit Finaled 9/9/2025 RUBEN SALAS
CofO Issued 9/9/2025 RUBEN SALAS
Permit Finaled 9/9/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/25/2021 ADRIAN CASTRO
ZI Cleared 6/29/2021 MIGUEL GAMBOA
Sewer availability Cleared 7/12/2021 ROSE MARIE SMITH
Hydrant and Access approval Cleared 11/4/2021 GILBERT URREA
Low Impact Development Cleared 12/3/2021 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 12/13/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/13/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21500 WYANDOTTE ST 106      CANOGA PARK, CA 91303

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/7/2023 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 5/4/2023 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 5/23/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 6/15/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 6/15/2023 Corrections Issued RAUL OLAGI
Green Building Rough 6/15/2023 Approved RAUL OLAGI
HVAC-Rough 6/15/2023 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 6/15/2023 Partial Approval RAUL OLAGI
PLUMBING-Rough 6/15/2023 Approved RAUL OLAGI
Verify Sprinkler Sign Off 6/15/2023 Approved RAUL OLAGI
ELECTRICAL-Rough 6/21/2023 Approved RAUL OLAGI
HVAC-Rough 6/21/2023 Approved RAUL OLAGI
Insulation 6/21/2023 Approved RAUL OLAGI
Shower Pan 6/21/2023 Approved RAUL OLAGI
Drywall Nailing 6/27/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 6/27/2023 Not Ready for Inspection RAUL OLAGI
Interior/Exterior Lathing 7/31/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 5/2/2025 Not Ready for Inspection SALVADOR MARTINEZ
Final 5/2/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Final 5/2/2025 Not Ready for Inspection SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 5/2/2025 SGSOV Not Ready SALVADOR MARTINEZ
Service/Power Release 5/2/2025 Not Ready for Inspection SALVADOR MARTINEZ
Smoke Detectors 5/2/2025 Not Ready for Inspection SALVADOR MARTINEZ
BUILDING-Rough-Frame 5/29/2025 Approved SALVADOR MARTINEZ
Final 5/29/2025 OK to Issue CofO SALVADOR MARTINEZ
Green Building Final 5/29/2025 Approved SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 5/29/2025 SGSOV Approved SALVADOR MARTINEZ
Service/Power Release 5/29/2025 Approved SALVADOR MARTINEZ
Smoke Detectors 5/29/2025 Approved SALVADOR MARTINEZ