11912 W CANTARA ST 91605

Certificate Information: 11912 W CANTARA ST 91605

Application / Permit
21010-20000-01460
Plan Check / Job No.
B21VN03698
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 40'-0" x 31'-6" ONE-STORY DET. ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d); ALL WORK PER ENGINEERING DESIGN
Permit Issued
Issued on 12/1/2021
Issuing Office
Current Status
CofO Issued on 9/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/26/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 SEAN SHAHMIRI
Corrections Issued 5/2/2021 SEAN SHAHMIRI
Quality Review Completed 5/17/2021 OMID HEDAYAT
Building Plans Picked Up 5/21/2021 APPLICANT
Applicant returned to address corrections 11/16/2021 SEAN SHAHMIRI
Plan Check Approved 12/1/2021 SEAN SHAHMIRI
Issued 12/1/2021 APPLICANT
CofO in Progress 8/4/2023 MATTHEW NELSON
Permit Finaled 9/12/2023 RUBEN SALAS
CofO Issued 9/12/2023 RUBEN SALAS
Permit Finaled 9/12/2023 RUBEN SALAS

Permit Application Clearance Information

Hydrant and Access approval Cleared 9/12/2021 RUEL COLE
Address approval Cleared 10/1/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 11/17/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 11/18/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 11/24/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/14/2022 Approved CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 3/29/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 4/5/2022 Partial Approval CHRISTOPHER DELLEFIELD
PLUMBING-Rough 4/5/2022 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 4/21/2022 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 6/1/2022 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 6/14/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Rough 6/14/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Verify Sprinkler Sign Off 6/14/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Wood Frame 6/14/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 7/6/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 7/6/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 7/6/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Verify Sprinkler Sign Off 7/6/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 8/23/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 8/23/2022 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 10/19/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 10/19/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 10/19/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Rough 10/19/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 10/19/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 12/21/2022 Approved MATTHEW NELSON
ELECTRICAL-Rough 12/21/2022 Approved MATTHEW NELSON
Green Building Rough 12/21/2022 Approved MATTHEW NELSON
HVAC-Rough 12/21/2022 Approved MATTHEW NELSON
Insulation 12/21/2022 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 12/21/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 12/28/2022 Approved MATTHEW NELSON
Drywall Nailing 1/5/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 2/23/2023 Partial Approval MATTHEW NELSON
Shower Pan 2/23/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 3/1/2023 Approved MATTHEW NELSON
Final 6/14/2023 Corrections Issued MATTHEW NELSON
Green Building Final 6/14/2023 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 6/14/2023 SGSOV Approved MATTHEW NELSON
Service/Power Release 6/14/2023 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 6/14/2023 Approved MATTHEW NELSON
Green Building Final 6/22/2023 Approved MATTHEW NELSON
PLUMBING-Final 6/22/2023 Approved MATTHEW NELSON
Service/Power Release 6/22/2023 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Final 7/5/2023 Not Ready for Inspection MATTHEW NELSON
Final 7/5/2023 Corrections Issued MATTHEW NELSON
Service/Power Release 7/5/2023 Not Ready for Inspection MATTHEW NELSON
Final 8/4/2023 OK to Issue CofO MATTHEW NELSON
Service/Power Release 8/4/2023 Approved MATTHEW NELSON