5714 N MAMMOTH AVE 91401
Certificate Information: 5714 N MAMMOTH AVE 91401
- Application / Permit
- 21010-20000-01459
- Plan Check / Job No.
- B21VN03670
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 22'4" X 36'5-1/2" TWO STORY DETACHED ACCESSORY DWELLING UNIT AS PER LAMC12.22.A.33(C) AND (E) WITH ATTACHED TWO CAR CARPORT, NFPA-13D FIRE SPRINKLERS REQUIRED , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 5/9/2022
- Issuing Office
- Current Status
- CofO in Progress on 4/29/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2021 | RARES BODEA |
| Corrections Issued | 4/11/2021 | RARES BODEA |
| Quality Review Completed | 4/21/2021 | STEVEN KIM |
| Applicant returned to address corrections | 9/27/2021 | RARES BODEA |
| Applicant returned to address corrections | 1/24/2022 | RARES BODEA |
| Applicant returned to address corrections | 2/22/2022 | RARES BODEA |
| Plan Check Approved | 4/21/2022 | RARES BODEA |
| Issued | 5/9/2022 | APPLICANT |
| CofO in Progress | 4/29/2026 | VINCENT HANLEY |
Permit Application Clearance Information
| Address approval | Cleared | 5/21/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 7/28/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 9/19/2021 | ROBERT DUFF |
| Construction near power lines | Cleared | 9/23/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 4/4/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 4/4/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | G N K Contruction; Lic. No.: 1052060-B | 6618 SMOKETREE AVE OAK PARK, CA 91377 |
| Engineer | Sarrami,, Gholamali F; Lic. No.: C43720 | 4942 HIGHLAND VIEW AVENUE LOS ANGELES, CA 90041 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/2/2022 | Partial Approval | RICHARD DOCKUS |
| Footing/Foundation/Slab | 6/9/2022 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 6/14/2022 | Approved | RICHARD DOCKUS |
| Deputy Drilled-In Anchors | 6/15/2022 | Conditional Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2022 | Corrections Issued | RICHARD DOCKUS |
| Wood Frame | 7/7/2022 | Partial Approval | RICHARD DOCKUS |
| Deputy Wood Construction | 7/15/2022 | Partial Approval | MATT KELLERMAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2023 | Partial Inspection | ROBERT GOLD |
| Rough-Elec/Plmb/HVAC | 2/11/2025 | Approved | RYAN SALAZAR |
| Special/Order Compliance | 12/9/2025 | Corrections Issued | RYAN SALAZAR |
| Service/Power Release | 1/5/2026 | Approved | RYAN SALAZAR |
| Special/Order Compliance | 2/20/2026 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/19/2026 | Approved | VINCENT HANLEY |
| Drywall Nailing | 3/19/2026 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 3/19/2026 | Approved | VINCENT HANLEY |
| Final | 3/19/2026 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 3/19/2026 | Approved | VINCENT HANLEY |
| Green Building Rough | 3/19/2026 | Approved | VINCENT HANLEY |
| HVAC-Final | 3/19/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 3/19/2026 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 3/19/2026 | SGSOV Not Required | VINCENT HANLEY |
| Smoke Detectors | 3/19/2026 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 3/19/2026 | Approved | VINCENT HANLEY |
| Final | 4/28/2026 | OK to Issue CofO | VINCENT HANLEY |