5712 N MAMMOTH AVE 91401
Certificate Information: 5712 N MAMMOTH AVE 91401
- Application / Permit
- 21010-20000-01452
- Plan Check / Job No.
- B21VN03670
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 55.5' X 37' ONE STORY SINGLE FAMILLY DWELLING , NFPA-13D FIRE SPRINKLERS REQUIRED, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 5/9/2022
- Issuing Office
- Current Status
- CofO in Progress on 4/28/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2021 | RARES BODEA |
| Corrections Issued | 4/11/2021 | RARES BODEA |
| Quality Review Completed | 4/21/2021 | STEVEN KIM |
| Applicant returned to address corrections | 9/27/2021 | RARES BODEA |
| Applicant returned to address corrections | 1/24/2022 | RARES BODEA |
| Applicant returned to address corrections | 2/22/2022 | RARES BODEA |
| Plan Check Approved | 4/21/2022 | RARES BODEA |
| Issued | 5/9/2022 | APPLICANT |
| CofO in Progress | 4/28/2026 | VINCENT HANLEY |
Permit Application Clearance Information
| Address approval | Cleared | 5/21/2021 | ADRIAN CASTRO |
| Permit | Cleared | 5/21/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 7/28/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 9/19/2021 | ROBERT DUFF |
| Trees in Parkway | Cleared | 1/11/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 4/4/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 4/4/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | G N K Contruction; Lic. No.: 1052060-B | 6618 SMOKETREE AVE OAK PARK, CA 91377 |
| Engineer | Sarrami,, Gholamali F; Lic. No.: C43720 | 4942 HIGHLAND VIEW AVENUE LOS ANGELES, CA 90041 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/2/2022 | Partial Approval | RICHARD DOCKUS |
| Footing/Foundation/Slab | 6/8/2022 | Approved | RICHARD DOCKUS |
| Sewer | 6/8/2022 | Approved | RICHARD DOCKUS |
| Deputy Drilled-In Anchors | 6/15/2022 | Conditional Approval | RICHARD DOCKUS |
| Deputy Wood Construction | 7/7/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 9/9/2022 | Corrections Issued | RICHARD DOCKUS |
| ELECTRICAL-Rough | 9/21/2022 | No Access for Inspection | JACK KARGODORIAN |
| Pre-Inspection | 10/10/2023 | Partial Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2023 | Partial Inspection | ROBERT GOLD |
| ELECTRICAL-Rough | 1/29/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Pre-Inspection | 1/29/2025 | Partial Inspection | RYAN SALAZAR |
| ELECTRICAL-Rough | 2/10/2025 | Not Ready for Inspection | RYAN SALAZAR |
| HVAC-Rough | 2/10/2025 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Rough | 2/10/2025 | Not Ready for Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 2/11/2025 | Corrections Issued | RYAN SALAZAR |
| Rough-Elec/Plmb/HVAC | 2/11/2025 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2025 | Approved | RYAN SALAZAR |
| Shower Pan | 5/2/2025 | Approved | RYAN SALAZAR |
| Insulation | 7/1/2025 | Corrections Issued | MATTHEW NELSON |
| Interior/Exterior Lathing | 7/1/2025 | Approved | MATTHEW NELSON |
| Insulation | 7/3/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/3/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 7/17/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 7/17/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 12/4/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 12/4/2025 | Approved | RYAN SALAZAR |
| Special/Order Compliance | 12/9/2025 | Corrections Issued | RYAN SALAZAR |
| Service/Power Release | 1/5/2026 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 2/19/2026 | Approved | VINCENT HANLEY |
| Final | 2/19/2026 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 2/19/2026 | Approved | VINCENT HANLEY |
| HVAC-Final | 2/19/2026 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 2/19/2026 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 2/19/2026 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 2/19/2026 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 2/23/2026 | Corrections Issued | VINCENT HANLEY |
| Order to Comply | 2/23/2026 | OTC Issued | VINCENT HANLEY |
| Final | 3/17/2026 | Partial Approval | VINCENT HANLEY |
| Final | 4/28/2026 | OK to Issue CofO | VINCENT HANLEY |