455 N BUNDY DR 90049
Certificate Information: 455 N BUNDY DR 90049
- Application / Permit
- 21010-20000-01449
- Plan Check / Job No.
- B21VN03656
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (61'-0"x 82'-0") TWO-STORY SINGLE FAMILY DWELLING WITH ATT. 2-CAR GARAGE, NFPA-13D ATUTOMATIC FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 7/27/2021
- Issuing Office
- Current Status
- CofO Issued on 8/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | TROY DEGUZMAN |
| Corrections Issued | 4/5/2021 | TROY DEGUZMAN |
| Quality Review Completed | 4/7/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 6/4/2021 | TROY DEGUZMAN |
| Plan Check Approved | 7/14/2021 | TROY DEGUZMAN |
| Issued | 7/27/2021 | APPLICANT |
| CofO in Progress | 8/22/2022 | MICHAEL PELHAM |
| Permit Finaled | 8/22/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/22/2022 | DANIEL ORRANTE |
| CofO Issued | 8/22/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/13/2021 | DINAH GARIN |
| Permit | Cleared | 4/13/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2021 | DINAH GARIN |
| Sewer availability | Cleared | 4/15/2021 | DINAH GARIN |
| Trees in Parkway | Cleared | 5/18/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 5/20/2021 | JOHN CONNEALLY |
| GPI Written Notices | Cleared | 6/4/2021 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 6/4/2021 | TROY DEGUZMAN |
| Green Code | Cleared | 6/4/2021 | TROY DEGUZMAN |
| Low Impact Development | Cleared | 7/6/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 7/8/2021 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/10/2021 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 9/14/2021 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 9/23/2021 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 9/23/2021 | Approved | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 9/24/2021 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 9/29/2021 | Partial Inspection | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2021 | Partial Approval | MATT KELLERMAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 11/8/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Gas Test | 11/8/2021 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 11/8/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 11/8/2021 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 11/18/2021 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 11/19/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 11/19/2021 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2021 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 11/19/2021 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 11/19/2021 | Approved | CARLOS MATAMOROS |
| Insulation | 12/1/2021 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/6/2021 | Corrections Issued | STEPHANIE SWANSON |
| Shower Pan | 12/6/2021 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 12/20/2021 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 12/20/2021 | Partial Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 2/11/2022 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 6/24/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Final | 6/24/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Final | 6/24/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Final | 6/24/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 6/24/2022 | Corrections Issued | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 6/24/2022 | SGSOV Approved | CARLOS MATAMOROS |
| Service/Power Release | 6/24/2022 | Not Required | CARLOS MATAMOROS |
| Smoke Detectors | 6/24/2022 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Final | 6/28/2022 | Approved | CARLOS MATAMOROS |
| Final | 6/28/2022 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Final | 6/28/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 6/28/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 6/28/2022 | Approved | CARLOS MATAMOROS |
| Smoke Detectors | 6/28/2022 | Approved | CARLOS MATAMOROS |
| Final | 8/22/2022 | Conditional Approval | MICHAEL PELHAM |