10154 N OSO AVE 91311
Certificate Information: 10154 N OSO AVE 91311
- Application / Permit
- 21010-20000-01330
- Plan Check / Job No.
- B21VN03280
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED (22'-6 1/2" x 34'-1/2"), 697 SQFT ADU PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 12/16/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | PETER MOSESIAN |
| Corrections Issued | 4/24/2021 | PETER MOSESIAN |
| Quality Review Completed | 5/7/2021 | OMID HEDAYAT |
| Plan Check Approved | 12/16/2021 | JON BLAINE |
| Issued | 12/16/2021 | APPLICANT |
| CofO in Progress | 3/29/2023 | DAVID SCANTLIN |
| Permit Finaled | 6/2/2023 | JOHN JANSON |
| CofO Issued | 6/2/2023 | JOHN JANSON |
| Permit Finaled | 6/2/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/23/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/24/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 8/12/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 10/26/2021 | GILBERT URREA |
| Low Impact Development | Cleared | 11/16/2021 | JONATAN VELASQUEZ |
| Roof/Waste drainage to street | Cleared | 11/18/2021 | DAGOVERTO GUERRERO |
Contact Information
| Architect | Gemigniani,, Richard Louis; Lic. No.: C18783 | 14263 VALLEY VISTA BLVD. SHERMAN OAKS, CA 91403 |
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/6/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 3/29/2022 | Partial Approval | TROY SANDERS |
| Underground Mechanical | 3/29/2022 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 5/23/2022 | Partial Approval | JEFFREY PARD |
| ELECTRICAL-Rough | 5/23/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 5/23/2022 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 5/23/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 5/23/2022 | Approved | JEFFREY PARD |
| Verify Sprinkler Sign Off | 5/23/2022 | Not Ready for Inspection | JEFFREY PARD |
| Insulation | 6/6/2022 | Approved | JEFFREY PARD |
| Drywall Nailing | 6/9/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 6/9/2022 | Approved | JEFFREY PARD |
| Shower Pan | 6/9/2022 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 6/14/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 1/19/2023 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 1/19/2023 | Approved | DAVID SCANTLIN |
| Final | 1/19/2023 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 1/19/2023 | Approved | DAVID SCANTLIN |
| HVAC-Final | 1/19/2023 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 1/19/2023 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 1/19/2023 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 1/19/2023 | Approved | DAVID SCANTLIN |
| Smoke Detectors | 1/19/2023 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 1/19/2023 | Approved | DAVID SCANTLIN |
| Final | 3/20/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 3/28/2023 | OK to Issue CofO | DAVID SCANTLIN |