1510 1/2 S REDONDO BLVD 90019
Certificate Information: 1510 1/2 S REDONDO BLVD 90019
- Application / Permit
- 21010-20000-01327
- Plan Check / Job No.
- B21VN03277
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 40' X 30' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A. 33(c) and (d). COMPLY WITH DEPARTMENT ORDER effective date 02/03/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 9/10/2021
- Issuing Office
- Current Status
- CofO Issued on 10/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 3/27/2021 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 9/4/2021 | JEROME MAGAT PALMA |
| Issued | 9/10/2021 | APPLICANT |
| Building Plans Picked Up | 9/15/2021 | APPLICANT |
| CofO in Progress | 10/10/2023 | WILLIAM MICHALAK |
| Permit Finaled | 10/23/2023 | BRUCE TODD |
| CofO Issued | 10/23/2023 | BRUCE TODD |
| Permit Finaled | 10/23/2023 | BRUCE TODD |
Permit Application Clearance Information
| Address approval | Cleared | 4/14/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2021 | JEANIE LAM |
| Sewer availability | Cleared | 4/14/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 5/21/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 8/13/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 8/17/2021 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/19/2021 | Corrections Issued | GLEN RAND |
| METHANE-Barrier | 11/19/2021 | Approved | GLEN RAND |
| METHANE-Subgrade | 11/19/2021 | Approved | GLEN RAND |
| Footing/Foundation/Slab | 11/23/2021 | Corrections Issued | GLEN RAND |
| BUILDING-Rough-Frame | 12/15/2021 | Partial Approval | GLEN RAND |
| PLUMBING-Rough | 12/15/2021 | Partial Approval | GLEN RAND |
| BUILDING-Rough-Frame | 2/23/2022 | Partial Approval | GLEN RAND |
| PLUMBING-Rough | 2/23/2022 | Approved | GLEN RAND |
| Rough-Elec/Plmb/HVAC | 2/23/2022 | Corrections Issued | GLEN RAND |
| Underground Mechanical | 2/23/2022 | Corrections Issued | GLEN RAND |
| ELECTRICAL-Rough | 2/24/2022 | Corrections Issued | GLEN RAND |
| BUILDING-Rough-Frame | 3/7/2022 | Approved | GLEN RAND |
| Green Building Rough | 3/7/2022 | Approved | GLEN RAND |
| METHANE-Rough | 3/7/2022 | Approved | GLEN RAND |
| Rough-Elec/Plmb/HVAC | 3/7/2022 | Corrections Issued | GLEN RAND |
| Interior/Exterior Lathing | 3/11/2022 | Approved | GLEN RAND |
| Insulation | 3/16/2022 | Corrections Issued | GLEN RAND |
| Drywall Nailing | 3/24/2022 | Approved | WILLIAM MICHALAK |
| Insulation | 4/12/2022 | Approved | GLEN RAND |
| ELECTRICAL-Rough | 7/27/2022 | Corrections Issued | GLEN RAND |
| PLUMBING-Rough | 7/27/2022 | Corrections Issued | GLEN RAND |
| Final | 9/28/2022 | Corrections Issued | GLEN RAND |
| Footing/Foundation/Slab | 9/28/2022 | Approved | GLEN RAND |
| Green Building Final | 9/28/2022 | Approved | GLEN RAND |
| SGSOV-Seismic Gas S/O Valve | 9/28/2022 | SGSOV Not Ready | GLEN RAND |
| Service/Power Release | 9/28/2022 | Corrections Issued | GLEN RAND |
| Smoke Detectors | 9/28/2022 | Approved | GLEN RAND |
| Final | 4/17/2023 | No Access for Inspection | GLEN RAND |
| SGSOV-Seismic Gas S/O Valve | 4/17/2023 | SGSOV Not Ready | GLEN RAND |
| Service/Power Release | 4/17/2023 | No Access for Inspection | GLEN RAND |
| Final | 5/8/2023 | Corrections Issued | GLEN RAND |
| SGSOV-Seismic Gas S/O Valve | 5/8/2023 | SGSOV Approved | GLEN RAND |
| ELECTRICAL-Final | 9/12/2023 | Approved | WILLIAM MICHALAK |
| Final | 9/12/2023 | Corrections Issued | WILLIAM MICHALAK |
| HVAC-Final | 9/12/2023 | Conditional Approval | WILLIAM MICHALAK |
| PLUMBING-Final | 9/12/2023 | Approved | WILLIAM MICHALAK |
| Service/Power Release | 9/12/2023 | Approved | WILLIAM MICHALAK |
| Final | 9/29/2023 | Conditional Approval | WILLIAM MICHALAK |
| Gas Test | 9/29/2023 | Approved | WILLIAM MICHALAK |