7034 1/2 N NESTLE AVE 91335

Certificate Information: 7034 1/2 N NESTLE AVE 91335

Application / Permit
21010-20000-01326
Plan Check / Job No.
B21VN03270
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 30' X 30' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A. 33(c) and (d)
Permit Issued
Issued on 11/4/2021
Issuing Office
Current Status
CofO Issued on 4/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2021 APPLICANT
Assigned to Plan Check Engineer 3/26/2021 JEROME MAGAT PALMA
Corrections Issued 3/27/2021 JEROME MAGAT PALMA
Applicant returned to address corrections 10/12/2021 JEROME MAGAT PALMA
Applicant returned to address corrections 10/25/2021 JEROME MAGAT PALMA
Plan Check Approved 11/3/2021 JEROME MAGAT PALMA
Issued 11/4/2021 APPLICANT
Building Plans Picked Up 11/5/2021 APPLICANT
CofO in Progress 3/31/2022 VINCENT HANLEY
CofO Issued 4/28/2022 MICHAEL SMITH
Permit Finaled 4/28/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/5/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/5/2021 ADRIAN CASTRO
Sewer availability Cleared 4/5/2021 ADRIAN CASTRO
Hydrant and Access approval Cleared 5/27/2021 MATTHEW CRAIG
Construction near power lines Cleared 8/12/2021 RIDWAN HARDY
Low Impact Development Cleared 9/29/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 9/30/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/29/2021 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 12/1/2021 Approved VINCENT HANLEY
Footing/Foundation/Slab 12/1/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/20/2021 Approved PETER FOLLING
ELECTRICAL-Rough 1/3/2022 Approved DAVID SCANTLIN
Green Building Rough 1/3/2022 Approved DAVID SCANTLIN
HVAC-Rough 1/3/2022 Approved DAVID SCANTLIN
PLUMBING-Rough 1/3/2022 Approved DAVID SCANTLIN
Insulation 1/6/2022 Approved SEAN HAUPT
Shower Pan 1/6/2022 Approved SEAN HAUPT
Drywall Nailing 1/18/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 1/18/2022 Approved VINCENT HANLEY
Sewer 1/18/2022 Approved VINCENT HANLEY
Underground Mechanical 1/18/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 3/14/2022 SGSOV Not Ready VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 3/17/2022 SGSOV Not Ready VINCENT HANLEY
BUILDING-Rough-Frame 3/25/2022 Partial Approval VINCENT HANLEY
ELECTRICAL-Final 3/25/2022 Corrections Issued VINCENT HANLEY
Final 3/25/2022 Corrections Issued VINCENT HANLEY
Green Building Final 3/25/2022 Approved VINCENT HANLEY
HVAC-Final 3/25/2022 Corrections Issued VINCENT HANLEY
PLUMBING-Final 3/25/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 3/25/2022 SGSOV Approved VINCENT HANLEY
Service/Power Release 3/25/2022 Approved VINCENT HANLEY
Smoke Detectors 3/25/2022 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 3/25/2022 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 3/31/2022 Approved VINCENT HANLEY
ELECTRICAL-Final 3/31/2022 Approved VINCENT HANLEY
Final 3/31/2022 OK to Issue CofO VINCENT HANLEY
HVAC-Final 3/31/2022 Approved VINCENT HANLEY
PLUMBING-Final 3/31/2022 Approved VINCENT HANLEY
Service/Power Release 3/31/2022 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 3/31/2022 Not Ready for Inspection VINCENT HANLEY