1822 N VISTA ST 90046

Certificate Information: 1822 N VISTA ST 90046

Application / Permit
21010-20000-01309
Plan Check / Job No.
B21VN03229
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 12' X 19' DETACHED REC ROOM
Permit Issued
Issued on 8/11/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 SELLA BENYAMIN
Corrections Issued 3/31/2021 SELLA BENYAMIN
Quality Review Completed 4/5/2021 STEVEN KIM
Building Plans Picked Up 9/15/2021 APPLICANT
Applicant returned to address corrections 4/18/2022 SELLA BENYAMIN
Applicant returned to address corrections 6/8/2022 SELLA BENYAMIN
Plan Check Approved 7/28/2022 SELLA BENYAMIN
Issued 8/11/2022 APPLICANT
CofO in Progress 4/16/2024 BRIAN SULLIVAN
Permit Finaled 4/16/2024 RONALD MYRICK
CofO Issued 4/16/2024 RONALD MYRICK
Permit Finaled 4/16/2024 RONALD MYRICK

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 2/22/2022 CINDY QI
BHO/Hillside ordinance Cleared 2/22/2022 CINDY QI
BHO/Hillside ordinance Cleared 2/22/2022 CINDY QI
BHO/Hillside ordinance Cleared 2/22/2022 CINDY QI
BHO/Hillside ordinance Cleared 2/22/2022 CINDY QI
Roof/Waste drainage to street Cleared 3/7/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 3/8/2022 CINDY QI
Low Impact Development Cleared 3/21/2022 MITESH PATEL
GPI Written Notices Cleared 7/28/2022 SELLA BENYAMIN
Grading Pre-Inspection Cleared 7/28/2022 SELLA BENYAMIN

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/23/2023 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 6/7/2023 Approved BRIAN SULLIVAN
Deputy Reinf. Concrete 6/8/2023 Conditional Approval BRIAN SULLIVAN
PLUMBING-Rough 8/22/2023 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 8/31/2023 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 8/31/2023 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 9/7/2023 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Rough 9/7/2023 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Partial Approval BRIAN SULLIVAN
Green Building Rough 9/7/2023 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 9/7/2023 Not Ready for Inspection BRIAN SULLIVAN
Interior/Exterior Lathing 9/25/2023 Partial Approval BRIAN SULLIVAN
Drywall Nailing 9/28/2023 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 10/3/2023 Approved BRIAN SULLIVAN
ELECTRICAL-Final 3/1/2024 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Final 3/8/2024 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 4/3/2024 Approved BRIAN SULLIVAN
Final 4/3/2024 Corrections Issued BRIAN SULLIVAN
Green Building Final 4/3/2024 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 4/3/2024 SGSOV Approved BRIAN SULLIVAN
Service/Power Release 4/3/2024 Approved BRIAN SULLIVAN
Smoke Detectors 4/3/2024 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 4/3/2024 Approved BRIAN SULLIVAN
Final 4/16/2024 OK to Issue CofO BRIAN SULLIVAN