8409 N AURA AVE 91324
Certificate Information: 8409 N AURA AVE 91324
- Application / Permit
- 21010-20000-01285
- Plan Check / Job No.
- B21VN03165
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 29' X 38' 5" IRR.SHAPED 1-STORY ADU WITH ATTACHED 12' 6" X 20' OPEN TRELLIS. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 2/1/2022
- Issuing Office
- Current Status
- CofO Issued on 6/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 3/27/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 12/3/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 2/1/2022 | GURUNATH NESARAJAH |
| Issued | 2/1/2022 | APPLICANT |
| Building Plans Picked Up | 2/4/2022 | APPLICANT |
| CofO in Progress | 5/2/2022 | JEFFREY PARD |
| Permit Finaled | 6/28/2022 | JOHN JANSON |
| CofO Issued | 6/28/2022 | JOHN JANSON |
| Permit Finaled | 6/28/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/13/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 5/14/2021 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 5/21/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 7/23/2021 | MATTHEW CRAIG |
| ZA Case | Cleared | 8/23/2021 | DANG NGUYEN |
| ZI | Cleared | 8/23/2021 | DANG NGUYEN |
| Low Impact Development | Cleared | 11/18/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 1/13/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Papazyan,, Andranik; Lic. No.: C56824 | 635 W COLORADO ST STE 104 GLENDALE, CA 91204 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/4/2022 | Approved | JEFFREY PARD |
| Rough-Elec/Plmb/HVAC | 2/9/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 2/16/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 2/16/2022 | Approved | JEFFREY PARD |
| Verify Sprinkler Sign Off | 2/16/2022 | Approved | JEFFREY PARD |
| Insulation | 2/22/2022 | No Access for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 3/1/2022 | Partial Approval | JEFFREY PARD |
| Drywall Nailing | 3/7/2022 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 3/7/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 3/15/2022 | Approved | JEFFREY PARD |
| Final | 3/15/2022 | Corrections Issued | JEFFREY PARD |
| Green Building Final | 3/15/2022 | Corrections Issued | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 3/15/2022 | SGSOV Approved | JEFFREY PARD |
| Service/Power Release | 3/15/2022 | Approved | JEFFREY PARD |
| Smoke Detectors | 3/15/2022 | Approved | JEFFREY PARD |
| Final | 4/5/2022 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Final | 4/5/2022 | Approved | JEFFREY PARD |
| Final | 4/29/2022 | OK to Issue CofO | JEFFREY PARD |