5344 E ALLAN ST 90032

Certificate Information: 5344 E ALLAN ST 90032

Application / Permit
21010-20000-01270
Plan Check / Job No.
B21VN03123
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED (30'-0" x 20'-0"),600 SQFT ADU PER LAMC 12.22 A.33 (c)(d)
Permit Issued
Issued on 10/6/2021
Issuing Office
Current Status
Issued on 10/6/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/16/2021 APPLICANT
Assigned to Plan Check Engineer 4/15/2021 PETER MOSESIAN
Corrections Issued 4/21/2021 PETER MOSESIAN
Quality Review Completed 5/7/2021 OMID HEDAYAT
Plan Check Approved 10/6/2021 PETER MOSESIAN
Issued 10/6/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/23/2021 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 4/27/2021 ELAINE LEI
Sewer availability Cleared 4/27/2021 ELAINE LEI
Grading Pre-Inspection Cleared 6/1/2021 PATRICK MISCHLICH
Hydrant and Access approval Cleared 6/2/2021 MATTHEW CRAIG
Construction near power lines Cleared 7/13/2021 RIDWAN HARDY
Low Impact Development Cleared 8/31/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 9/2/2021 THAN WIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/3/2022 Partial Approval COREY HUPP
Footing/Foundation/Slab 2/11/2022 Corrections Issued RUBEN SALAS
Pre-Inspection 2/16/2022 Corrections Issued COREY HUPP
Footing/Foundation/Slab 2/28/2022 No Access for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 3/11/2022 Approved COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 6/9/2022 Approved AMY COLIN
Interior/Exterior Lathing 6/22/2022 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 8/16/2022 Approved AMY COLIN
ELECTRICAL-Rough 8/16/2022 Approved AMY COLIN
Green Building Rough 8/16/2022 Approved AMY COLIN
PLUMBING-Rough 8/16/2022 Partial Approval AMY COLIN
Verify Sprinkler Sign Off 8/16/2022 Approved AMY COLIN
Insulation 8/19/2022 Approved RUBEN SALAS
Shower Pan 8/22/2022 Approved RUBEN SALAS
Drywall Nailing 9/6/2022 Approved OSVALDO PARAMO
Sewer 9/19/2022 Partial Approval AMY COLIN
Sewer 10/6/2022 Approved AMY COLIN
ELECTRICAL-Final 12/20/2024 Not Ready for Inspection LILIANA PORTILLO
Final 12/20/2024 Corrections Issued LILIANA PORTILLO
Green Building Final 12/20/2024 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 12/20/2024 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 12/20/2024 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 12/20/2024 Not Ready for Inspection LILIANA PORTILLO
Final 3/6/2026 Corrections Issued LILIANA PORTILLO
Green Building Final 3/6/2026 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 3/6/2026 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 3/6/2026 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 3/6/2026 Not Ready for Inspection LILIANA PORTILLO