1935 S BUTLER AVE 90025

Certificate Information: 1935 S BUTLER AVE 90025

Application / Permit
21010-20000-01268
Plan Check / Job No.
B21VN03112
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 2 STORY ACCESSORY DWELLING UNIT per LAMC 12.22 A.33(c) and (d) (28'-8"x25'-7")
Permit Issued
Issued on 6/2/2022
Issuing Office
Current Status
CofO Issued on 2/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 MOHAMMAD ESMAILI
Corrections Issued 5/3/2021 MOHAMMAD ESMAILI
Quality Review Completed 5/13/2021 OMID HEDAYAT
Building Plans Picked Up 5/14/2021 APPLICANT
Applicant returned to address corrections 5/11/2022 MOHAMMAD ESMAILI
Plan Check Approved 5/20/2022 MOHAMMAD ESMAILI
Issued 6/2/2022 APPLICANT
CofO in Progress 1/31/2024 ARAM AVEDISIAN
Permit Finaled 2/5/2024 DANIEL ORRANTE
CofO Issued 2/5/2024 DANIEL ORRANTE
Permit Finaled 2/5/2024 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 5/14/2021 LOUIS ORTEGA
ZI Cleared 5/14/2021 LOUIS ORTEGA
Specific Plan Cleared 5/25/2021 FREDDY GARCIA
Construction near power lines Cleared 5/29/2021 RIDWAN HARDY
Address approval Cleared 6/1/2021 OSCAR GUTIERREZ
Hydrant and Access approval Cleared 8/3/2021 MATTHEW CRAIG
Specific Plan Cleared 3/29/2022 LOUIS ORTEGA
Low Impact Development Cleared 4/19/2022 ORVAL HERNANDEZ-MARCI
Sewer availability Cleared 4/28/2022 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 4/29/2022 CATHERINE ADROVER
Roof/Waste drainage to street Cleared 4/29/2022 CATHERINE ADROVER

Contact Information

Architect Manligas,, Amorsolo Rubio; Lic. No.: C15983 1120 LITTLE ROCK WAY      LAS VEGAS, NV 89123
Contractor Owner-Builder       ,

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/17/2023 Not Ready for Inspection STEPHANIE SWANSON
Pre-Inspection 2/17/2023 Partial Inspection STEPHANIE SWANSON
Footing/Foundation/Slab 5/1/2023 Approved JESUS PINEDA
BUILDING-Rough-Frame 5/10/2023 Partial Approval HERBERT GIRON
Insulation 5/10/2023 Partial Approval HERBERT GIRON
PLUMBING-Rough 5/10/2023 Partial Approval HERBERT GIRON
Wood Frame 5/10/2023 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 5/12/2023 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/19/2023 Partial Approval JESUS PINEDA
Wood Frame 5/19/2023 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 6/20/2023 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 6/30/2023 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 7/5/2023 Approved JEREMY TODD
Green Building Rough 7/5/2023 Approved JEREMY TODD
HVAC-Rough 7/5/2023 Partial Inspection JEREMY TODD
PLUMBING-Rough 7/5/2023 Approved JEREMY TODD
Verify Sprinkler Sign Off 7/5/2023 Approved JEREMY TODD
Wood Frame 7/5/2023 Approved JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Approved JEREMY TODD
Interior/Exterior Lathing 7/13/2023 Approved JEREMY TODD
BUILDING-Rough-Frame 7/28/2023 Corrections Issued MICHAEL PELHAM
Insulation 7/28/2023 Corrections Issued MICHAEL PELHAM
BUILDING-Rough-Frame 8/1/2023 Approved MICHAEL PELHAM
Final 8/1/2023 Corrections Issued MICHAEL PELHAM
HVAC-Rough 8/1/2023 Approved MICHAEL PELHAM
Insulation 8/1/2023 Approved MICHAEL PELHAM
Drywall Nailing 8/11/2023 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 8/24/2023 Approved CHRISTOPHER WILSON
Shower Pan 8/24/2023 Approved CHRISTOPHER WILSON
Gas Test 10/10/2023 Not Ready for Inspection EVAN COOPER
Sewer 10/10/2023 Corrections Issued EVAN COOPER
Sewer 10/16/2023 Corrections Issued BEN MOLSTAD
Sewer 10/18/2023 Approved BEN MOLSTAD
Gas Test 10/23/2023 Approved BEN MOLSTAD
Underground Mechanical 10/23/2023 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Final 12/7/2023 Corrections Issued BEN MOLSTAD
Final 12/7/2023 Not Ready for Inspection BEN MOLSTAD
Green Building Final 12/7/2023 Not Ready for Inspection BEN MOLSTAD
HVAC-Final 12/7/2023 Corrections Issued BEN MOLSTAD
PLUMBING-Final 12/7/2023 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 12/7/2023 SGSOV Not Ready BEN MOLSTAD
Service/Power Release 12/7/2023 Not Ready for Inspection BEN MOLSTAD
Smoke Detectors 12/7/2023 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Final 12/12/2023 Corrections Issued BEN MOLSTAD
HVAC-Final 12/12/2023 Corrections Issued BEN MOLSTAD
PLUMBING-Final 12/12/2023 Approved BEN MOLSTAD
ELECTRICAL-Final 12/20/2023 Corrections Issued BEN MOLSTAD
HVAC-Final 12/20/2023 Approved BEN MOLSTAD
ELECTRICAL-Final 12/29/2023 Corrections Issued BEN MOLSTAD
ELECTRICAL-Final 1/30/2024 Approved ARAM AVEDISIAN
Final 1/30/2024 OK to Issue CofO ARAM AVEDISIAN
Green Building Final 1/30/2024 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 1/30/2024 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 1/30/2024 Approved ARAM AVEDISIAN
Smoke Detectors 1/30/2024 Approved ARAM AVEDISIAN