724 N OGDEN DR 90046
Certificate Information: 724 N OGDEN DR 90046
- Application / Permit
- 21010-20000-01267
- Plan Check / Job No.
- B21VN03110
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW 19' X 19' DETACHED GARAGE
- Permit Issued
- Issued on 8/23/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | SELLA BENYAMIN |
| Corrections Issued | 4/27/2021 | SELLA BENYAMIN |
| Quality Review Completed | 5/5/2021 | STEVEN KIM |
| Applicant returned to address corrections | 7/12/2022 | SELLA BENYAMIN |
| Plan Check Approved | 8/19/2022 | SELLA BENYAMIN |
| Issued | 8/23/2022 | APPLICANT |
| CofO in Progress | 5/23/2024 | AMIR NAZARIAN |
| Permit Finaled | 5/29/2024 | DEROLD HAUFF |
| CofO Issued | 5/29/2024 | DEROLD HAUFF |
| Permit Finaled | 5/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/11/2022 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2022 | WALLIE JONG |
| Low Impact Development | Cleared | 8/12/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 8/12/2022 | AMAAN MALIK |
Contact Information
| Contractor | Norman Construction; Lic. No.: 535530-B | 17614 SUPERIOR STREET NORTHRIDGE, CA 91325 |
| Engineer | Shachar,, Shaul Shkory; Lic. No.: C29686 | 18208 EMELITA ST TARZANA, CA 91356 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/7/2023 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 3/7/2023 | Approved | JEFFREY MEAD |
| METHANE-Barrier | 3/7/2023 | Approved | JEFFREY MEAD |
| METHANE-Subgrade | 3/7/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 5/26/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 5/26/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2023 | Corrections Issued | LILIANA PORTILLO |
| METHANE-Rough | 5/26/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 7/25/2023 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 7/25/2023 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/16/2023 | Approved | LILIANA PORTILLO |
| Insulation | 8/16/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/16/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 8/25/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 4/16/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 4/16/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Final | 4/16/2024 | Approved | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 4/16/2024 | SGSOV Approved | AMIR NAZARIAN |
| Service/Power Release | 4/16/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Smoke Detectors | 4/16/2024 | Approved | AMIR NAZARIAN |
| ELECTRICAL-Final | 5/2/2024 | Approved | AMIR NAZARIAN |
| Final | 5/2/2024 | Corrections Issued | AMIR NAZARIAN |
| Service/Power Release | 5/2/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Final | 5/22/2024 | OK to Issue CofO | AMIR NAZARIAN |
| Service/Power Release | 5/22/2024 | Approved | AMIR NAZARIAN |