724 N OGDEN DR 90046

Certificate Information: 724 N OGDEN DR 90046

Application / Permit
21010-20000-01267
Plan Check / Job No.
B21VN03110
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW 19' X 19' DETACHED GARAGE
Permit Issued
Issued on 8/23/2022
Issuing Office
Valley
Current Status
CofO Issued on 5/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 SELLA BENYAMIN
Corrections Issued 4/27/2021 SELLA BENYAMIN
Quality Review Completed 5/5/2021 STEVEN KIM
Applicant returned to address corrections 7/12/2022 SELLA BENYAMIN
Plan Check Approved 8/19/2022 SELLA BENYAMIN
Issued 8/23/2022 APPLICANT
CofO in Progress 5/23/2024 AMIR NAZARIAN
Permit Finaled 5/29/2024 DEROLD HAUFF
CofO Issued 5/29/2024 DEROLD HAUFF
Permit Finaled 5/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 4/11/2022 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 8/11/2022 WALLIE JONG
Low Impact Development Cleared 8/12/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/12/2022 AMAAN MALIK

Contact Information

Contractor Norman Construction; Lic. No.: 535530-B 17614 SUPERIOR STREET      NORTHRIDGE, CA 91325
Engineer Shachar,, Shaul Shkory; Lic. No.: C29686 18208 EMELITA ST      TARZANA, CA 91356

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/7/2023 Approved JEFFREY MEAD
Footing/Foundation/Slab 3/7/2023 Approved JEFFREY MEAD
METHANE-Barrier 3/7/2023 Approved JEFFREY MEAD
METHANE-Subgrade 3/7/2023 Approved JEFFREY MEAD
BUILDING-Rough-Frame 5/26/2023 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 5/26/2023 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 5/26/2023 Corrections Issued LILIANA PORTILLO
METHANE-Rough 5/26/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 7/25/2023 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 7/25/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Rough 7/25/2023 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 8/16/2023 Approved LILIANA PORTILLO
Insulation 8/16/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 8/16/2023 Approved LILIANA PORTILLO
Drywall Nailing 8/25/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 4/16/2024 Corrections Issued AMIR NAZARIAN
Final 4/16/2024 Corrections Issued AMIR NAZARIAN
Green Building Final 4/16/2024 Approved AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 4/16/2024 SGSOV Approved AMIR NAZARIAN
Service/Power Release 4/16/2024 Not Ready for Inspection AMIR NAZARIAN
Smoke Detectors 4/16/2024 Approved AMIR NAZARIAN
ELECTRICAL-Final 5/2/2024 Approved AMIR NAZARIAN
Final 5/2/2024 Corrections Issued AMIR NAZARIAN
Service/Power Release 5/2/2024 Not Ready for Inspection AMIR NAZARIAN
Final 5/22/2024 OK to Issue CofO AMIR NAZARIAN
Service/Power Release 5/22/2024 Approved AMIR NAZARIAN