724 N OGDEN DR 90046
Certificate Information: 724 N OGDEN DR 90046
- Application / Permit
- 21010-20000-01266
- Plan Check / Job No.
- B21VN03110
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SINGLE FAMILY DWELLING; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 8/23/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | SELLA BENYAMIN |
| Corrections Issued | 4/27/2021 | SELLA BENYAMIN |
| Quality Review Completed | 5/5/2021 | STEVEN KIM |
| Applicant returned to address corrections | 7/12/2022 | SELLA BENYAMIN |
| Plan Check Approved | 8/19/2022 | SELLA BENYAMIN |
| Issued | 8/23/2022 | APPLICANT |
| CofO in Progress | 5/28/2024 | AMIR NAZARIAN |
| Permit Finaled | 5/29/2024 | DEROLD HAUFF |
| CofO Issued | 5/29/2024 | DEROLD HAUFF |
| Permit Finaled | 5/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Permit | Cleared | 7/8/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2021 | CECILIO NAVARRO |
| Trees in Parkway | Cleared | 2/3/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 4/28/2022 | TA ANH |
| Hydrant and Access approval | Cleared | 6/10/2022 | LAVEON RIDER |
| Roof/Waste drainage to street | Cleared | 6/14/2022 | THAN WIN |
| Sewer availability | Cleared | 6/22/2022 | JEANETTE VONG |
Contact Information
| Contractor | Norman Construction; Lic. No.: 535530-B | 17614 SUPERIOR STREET NORTHRIDGE, CA 91325 |
| Engineer | Shachar,, Shaul Shkory; Lic. No.: C29686 | 18208 EMELITA ST TARZANA, CA 91356 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/8/2022 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2022 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 10/4/2022 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2022 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2023 | Approved | MICHAEL LEWIS |
| Deputy Wood Construction | 3/7/2023 | Partial Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 4/25/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 4/25/2023 | Approved | MICHAEL LEWIS |
| METHANE-Rough | 4/25/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 4/25/2023 | Approved | MICHAEL LEWIS |
| Shower Pan | 4/25/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 5/5/2023 | Corrections Issued | LILIANA PORTILLO |
| Green Building Rough | 5/5/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Interior/Exterior Lathing | 5/5/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 5/5/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 5/26/2023 | Conditional Approval | LILIANA PORTILLO |
| Green Building Rough | 5/26/2023 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 5/26/2023 | Partial Approval | LILIANA PORTILLO |
| Deputy Wood Construction | 6/1/2023 | Conditional Approval | LILIANA PORTILLO |
| Green Building Rough | 6/5/2023 | Approved | LILIANA PORTILLO |
| Insulation | 6/5/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 6/14/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 6/14/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 1/31/2024 | Approved | BRENDAN MORELLI |
| Gas Test | 1/31/2024 | Approved | BRENDAN MORELLI |
| Service/Power Release | 1/31/2024 | Approved | BRENDAN MORELLI |
| Smoke Detectors | 1/31/2024 | Approved | BRENDAN MORELLI |
| Verify Rec and Parks Fee Memo | 1/31/2024 | Approved | BRENDAN MORELLI |
| Green Building Final | 4/10/2024 | Approved | AMIR NAZARIAN |
| HVAC-Final | 4/10/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Final | 4/10/2024 | Approved | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 4/10/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| HVAC-Final | 4/16/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Final | 4/16/2024 | Approved | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 5/22/2024 | Approved | AMIR NAZARIAN |
| Final | 5/22/2024 | OK to Issue CofO | AMIR NAZARIAN |
| Footing/Foundation/Slab | 5/22/2024 | Approved | AMIR NAZARIAN |
| METHANE-Barrier | 5/22/2024 | Approved | AMIR NAZARIAN |
| METHANE-Subgrade | 5/22/2024 | Approved | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 5/22/2024 | SGSOV Approved | AMIR NAZARIAN |