1953 S BUTLER AVE 90025
Certificate Information: 1953 S BUTLER AVE 90025
- Application / Permit
- 21010-20000-01224
- Plan Check / Job No.
- B21VN03010
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 65' X 28' THREE STORY SINGLE FAMILY DWELLING WITH ATTACHED (1) CAR GARAGE , NFPA-13D FIRE SPRINKLERS REQUIRED, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 3/9/2023
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 3/9/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2021 | RARES BODEA |
| Corrections Issued | 4/18/2021 | RARES BODEA |
| Quality Review Completed | 5/3/2021 | STEVEN KIM |
| Applicant returned to address corrections | 11/14/2022 | RARES BODEA |
| Plan Check Approved | 2/13/2023 | RARES BODEA |
| Issued | 3/9/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/14/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 10/22/2021 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 1/10/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 5/11/2022 | SUNG JOON WON |
| Trees in Parkway | Cleared | 7/22/2022 | ADALBERTO VERA |
| Specific Plan | Cleared | 10/11/2022 | VALERIA CEJA |
| Permit | Cleared | 11/17/2022 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 11/17/2022 | ANTHONY MAINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong Lap; Lic. No.: C70784 | 20493 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/27/2023 | Corrections Issued | JESUS PINEDA |
| Excavation/Setback/Form/Re-Bar | 8/17/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/17/2023 | Partial Approval | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 8/28/2023 | Partial Approval | MICHAEL PELHAM |
| ELECTRICAL-Rough | 8/31/2023 | Partial Approval | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 9/12/2023 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Rough | 9/22/2023 | Approved | BEN MOLSTAD |
| Structural Steel Frame | 10/11/2023 | Approved | CARLOS MATAMOROS |
| Deck | 12/1/2023 | Not Ready for Inspection | BEN MOLSTAD |
| Deputy Wood Construction | 12/1/2023 | Conditional Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2023 | Conditional Approval | BEN MOLSTAD |
| BUILDING-Rough-Frame | 12/18/2023 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2023 | Conditional Approval | BEN MOLSTAD |
| Green Building Rough | 12/18/2023 | Not Ready for Inspection | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 12/18/2023 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 1/5/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 1/9/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 1/10/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 1/12/2024 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Rough | 1/16/2024 | Approved | BEN MOLSTAD |
| HVAC-Rough | 1/16/2024 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 1/17/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2024 | Partial Approval | BEN MOLSTAD |
| Green Building Rough | 1/17/2024 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 1/17/2024 | Corrections Issued | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 1/17/2024 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 1/24/2024 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 1/30/2024 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 1/30/2024 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 1/30/2024 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 1/30/2024 | Approved | ARAM AVEDISIAN |
| Insulation | 2/29/2024 | Corrections Issued | ASHLEY THOMPSON |
| Insulation | 3/20/2024 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 4/1/2024 | Partial Approval | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 6/17/2024 | Partial Approval | CARLOS MATAMOROS |
| Shower Pan | 6/24/2024 | Partial Approval | KIRK SANDERS |
| Insulation | 7/2/2024 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2024 | Corrections Issued | KIRK SANDERS |
| Deputy Wood Construction | 7/19/2024 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2024 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 12/13/2024 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 2/2/2026 | Partial Approval | EVAN COOPER |
| Wood Frame | 3/13/2026 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 3/16/2026 | Approved | DANIEL VERA |
| Drywall Nailing | 4/6/2026 | Partial Approval | ANDREW NAVE |
| Drywall Nailing | 4/17/2026 | Approved | ANDREW NAVE |
| Special/Order Compliance | 6/18/2026 | Partial Inspection | ANTHONY EGSON |