12528 W HORTENSE ST 91604

Certificate Information: 12528 W HORTENSE ST 91604

Application / Permit
21010-20000-01212
Plan Check / Job No.
B21VN02982
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (32'-0"x 25'-7") IRR SHAPE DETACHED ONE-STORY ACCESSORY DWELLING UNIT PER GCS 65852.2 (e), (1),(B) and LAMC 12.22 A.33 (c), (d) and (g). WORK PER ENGINEER.
Permit Issued
Issued on 10/13/2021
Issuing Office
Current Status
CofO Issued on 4/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2021 APPLICANT
Assigned to Plan Check Engineer 4/8/2021 TROY DEGUZMAN
Corrections Issued 4/9/2021 TROY DEGUZMAN
Quality Review Completed 4/13/2021 CHON CHIO KUO
Plan Check Approved 9/22/2021 TROY DEGUZMAN
Issued 10/13/2021 APPLICANT
CofO in Progress 4/4/2023 CHRISTOPHE COCHRAN
Permit Finaled 4/19/2023 MICHAEL SMITH
CofO Issued 4/19/2023 MICHAEL SMITH
Permit Finaled 4/19/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/4/2021 GABRIEL ROBLES
Sewer availability Cleared 5/4/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 5/6/2021 GABRIEL ROBLES
Construction near power lines Cleared 6/3/2021 RIDWAN HARDY
Low Impact Development Cleared 9/8/2021 JORGE MEJIA LEMUS
Hydrant and Access approval Cleared 9/20/2021 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 9/21/2021 DAGOVERTO GUERRERO
Green Code Cleared 9/22/2021 TROY DEGUZMAN

Contact Information

Architect Mizuki,, Steve Massanori; Lic. No.: C22676 2155 VERDUGO BLVD # 330      MONTROSE, CA 91020
Contractor Red Rock General Construction Inc; Lic. No.: 754130-B 17714 CANDIA COURT      GRANADA HILLS, CA 91344
Engineer Durand,, Paul Henri; Lic. No.: S4222 611 N G ST      OXNARD, CA 93030

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/20/2022 Partial Approval ARAM AVEDISIAN
Underground Mechanical 1/20/2022 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 2/2/2022 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 2/14/2022 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 2/24/2022 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/16/2022 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 6/1/2022 Approved ARAM AVEDISIAN
Gas Test 6/1/2022 Partial Approval ARAM AVEDISIAN
HVAC-Rough 6/1/2022 Approved ARAM AVEDISIAN
PLUMBING-Rough 6/1/2022 Approved ARAM AVEDISIAN
Wood Frame 6/1/2022 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 6/8/2022 Partial Approval ARAM AVEDISIAN
Underground Mechanical 6/8/2022 Partial Approval ARAM AVEDISIAN
Insulation 7/11/2022 Approved MATT KELLERMAN
Drywall Nailing 7/15/2022 Approved CHRISTOPHE COCHRAN
Green Building Rough 7/15/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 8/9/2022 Approved CHRISTOPHE COCHRAN
Sewer 11/1/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 11/10/2022 Corrections Issued CHRISTOPHE COCHRAN
Service/Power Release 11/10/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Final 1/20/2023 Corrections Issued CHRISTOPHE COCHRAN
HVAC-Final 1/20/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 1/20/2023 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 2/9/2023 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 2/9/2023 Approved CHRISTOPHE COCHRAN
Final 2/9/2023 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 2/9/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Final 2/9/2023 Approved CHRISTOPHE COCHRAN
MERV13>=Final 2/9/2023 Approved CHRISTOPHE COCHRAN
MERV13>=Rough 2/9/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 2/9/2023 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 2/9/2023 SGSOV Approved CHRISTOPHE COCHRAN
Service/Power Release 2/9/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 2/9/2023 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 2/9/2023 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 3/3/2023 Corrections Issued JUAN VALENZUELA
Final 3/3/2023 Not Ready for Inspection JUAN VALENZUELA
Green Building Final 3/3/2023 Corrections Issued JUAN VALENZUELA
Service/Power Release 3/3/2023 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Final 3/28/2023 Approved CHRISTOPHE COCHRAN
Final 3/28/2023 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 3/28/2023 Approved CHRISTOPHE COCHRAN
HVAC-Final 3/28/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 3/28/2023 Approved CHRISTOPHE COCHRAN
Service/Power Release 3/28/2023 Approved CHRISTOPHE COCHRAN
Final 4/4/2023 OK to Issue CofO CHRISTOPHE COCHRAN
PLUMBING-Final 4/4/2023 Approved CHRISTOPHE COCHRAN