9761 N PASO ROBLES AVE 91325
Certificate Information: 9761 N PASO ROBLES AVE 91325
- Application / Permit
- 21010-20000-01211
- Plan Check / Job No.
- B21VN02976
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 20'2"X40'2" 1-STORY DETACHED ADU PER LAMC 12.22 A.33(c) and (d) NFPA 13 D FIRE SPRINKLERS REQUIRED THROGUHOUT
- Permit Issued
- Issued on 3/14/2022
- Issuing Office
- Current Status
- CofO Issued on 2/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2021 | MARVEL DELACRUZ |
| Corrections Issued | 4/23/2021 | MARVEL DELACRUZ |
| Quality Review Completed | 4/29/2021 | STEVEN KIM |
| Applicant returned to address corrections | 1/31/2022 | MARVEL DELACRUZ |
| Plan Check Approved | 3/3/2022 | MARVEL DELACRUZ |
| Issued | 3/14/2022 | APPLICANT |
| CofO in Progress | 2/1/2023 | JOHN COLEMAN |
| Permit Finaled | 2/17/2023 | MICHAEL SMITH |
| CofO Issued | 2/17/2023 | MICHAEL SMITH |
| Permit Finaled | 2/17/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/29/2021 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 4/29/2021 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 4/29/2021 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 4/29/2021 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 4/29/2021 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 4/29/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/3/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 9/13/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/13/2021 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 12/7/2021 | GREGORY HOERNER |
| Low Impact Development | Cleared | 12/15/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 12/28/2021 | AMIR KASHFI |
| GPI Written Notices | Cleared | 1/31/2022 | MARVEL DELACRUZ |
| Grading Pre-Inspection | Cleared | 1/31/2022 | MARVEL DELACRUZ |
| Green Code | Cleared | 3/3/2022 | MARVEL DELACRUZ |
Contact Information
| Contractor | Pearl Remodeling; Lic. No.: 955824-B | 6803 YARMOUTH AVENUE RESEDA, CA 91335 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/4/2022 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 6/2/2022 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 6/28/2022 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 7/27/2022 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2022 | Partial Approval | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 8/31/2022 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 8/31/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/1/2022 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Rough | 9/1/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 9/1/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Insulation | 10/6/2022 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 10/6/2022 | Partial Approval | JAVIER RAMOS JR |
| Drywall Nailing | 10/18/2022 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Rough | 10/18/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 10/18/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 11/2/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Shower Pan | 11/2/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 11/9/2022 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2022 | No Access for Inspection | JAVIER RAMOS JR |
| Underground Mechanical | 11/17/2022 | No Access for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/24/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 1/24/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 1/24/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 1/24/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 1/24/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 1/24/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 1/24/2023 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 1/24/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 1/24/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 1/24/2023 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 1/24/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 1/31/2023 | Approved | JOHN COLEMAN |
| Final | 1/31/2023 | OK to Issue CofO | JOHN COLEMAN |
| Green Building Final | 1/31/2023 | Approved | JOHN COLEMAN |
| Service/Power Release | 1/31/2023 | Approved | JOHN COLEMAN |