17804 W HART ST 91335
Certificate Information: 17804 W HART ST 91335
- Application / Permit
- 21010-20000-01196
- Plan Check / Job No.
- B21VN02905
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 22' X 41' DETACHED 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(C) AND (D). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 10/15/2021
- Issuing Office
- Current Status
- CofO Issued on 5/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2021 | JENNIFER LEE |
| Corrections Issued | 3/30/2021 | JENNIFER LEE |
| Plan Check Approved | 10/14/2021 | JENNIFER LEE |
| Issued | 10/15/2021 | APPLICANT |
| Building Plans Picked Up | 10/15/2021 | APPLICANT |
| CofO in Progress | 11/1/2022 | JEFFREY BULL |
| No Progress | 4/8/2023 | MICHAEL PELHAM |
| CofO in Progress | 4/27/2023 | SEAN WIRCH |
| CofO in Progress | 5/25/2023 | SEAN WIRCH |
| CofO Issued | 5/25/2023 | JOHN JANSON |
| Permit Finaled | 5/25/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/7/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 4/7/2021 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 7/14/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 8/4/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/19/2021 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 10/3/2021 | KURT CORRAL |
Contact Information
| Contractor | Krn Construction And Remodeling Inc; Lic. No.: 1047372-B | 6433 TOPANGA CYN BLVD #483 CANOGA PARK, CA 91303 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/17/2021 | Partial Approval | VINCENT HANLEY |
| Underground Mechanical | 11/17/2021 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 11/24/2021 | Conditional Approval | DAVID SCANTLIN |
| Deputy Reinf. Concrete | 11/30/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 12/20/2021 | Not Ready for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2021 | Approved | PETER FOLLING |
| Green Building Rough | 12/20/2021 | Not Ready for Inspection | PETER FOLLING |
| Verify Sprinkler Sign Off | 12/20/2021 | Not Ready for Inspection | PETER FOLLING |
| Wood Frame | 12/20/2021 | Not Ready for Inspection | PETER FOLLING |
| Rough-Elec/Plmb/HVAC | 2/11/2022 | Corrections Issued | VINCENT HANLEY |
| Wood Frame | 2/11/2022 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/24/2022 | Approved | VINCENT HANLEY |
| HVAC-Rough | 2/24/2022 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 2/24/2022 | Approved | VINCENT HANLEY |
| HVAC-Rough | 3/3/2022 | Approved | VINCENT HANLEY |
| Insulation | 3/3/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 3/3/2022 | Partial Approval | MORRIS JACKSON |
| Drywall Nailing | 3/23/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 3/23/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/23/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 9/30/2022 | Approved | JEFFREY BULL |
| Final | 9/30/2022 | Corrections Issued | JEFFREY BULL |
| Footing/Foundation/Slab | 9/30/2022 | Approved | JEFFREY BULL |
| Green Building Final | 9/30/2022 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 9/30/2022 | SGSOV Approved | JEFFREY BULL |
| Service/Power Release | 9/30/2022 | Not Ready for Inspection | JEFFREY BULL |
| Smoke Detectors | 9/30/2022 | Approved | JEFFREY BULL |
| Verify Sprinkler Sign Off | 9/30/2022 | Approved | JEFFREY BULL |
| Final | 10/31/2022 | Partial Approval | JEFFREY BULL |
| Service/Power Release | 10/31/2022 | Approved | JEFFREY BULL |
| Special/Order Compliance | 4/28/2023 | Corrections Issued | SEAN WIRCH |