6108 W RODGERTON DR 90068

Certificate Information: 6108 W RODGERTON DR 90068

Application / Permit
21010-20000-01129
Plan Check / Job No.
B21VN02825
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 30'9"X49'4" 3-STORY SFD W/ATT 2-CAR 20'0"X21'0" ATTACHED GARAGE. NFPA13-D FIRE SPRINKLERS REQUIRED THROUGHOUT
Permit Issued
Issued on 4/21/2025
Issuing Office
Valley
Current Status
Issued on 4/21/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/10/2021 APPLICANT
Assigned to Plan Check Engineer 3/11/2021 MARVEL DELACRUZ
Corrections Issued 3/16/2021 MARVEL DELACRUZ
Quality Review Completed 3/24/2021 STEVEN KIM
Applicant returned to address corrections 8/2/2021 MARVEL DELACRUZ
Applicant returned to address corrections 2/14/2022 MARVEL DELACRUZ
Applicant returned to address corrections 9/12/2022 MARVEL DELACRUZ
Applicant returned to address corrections 7/1/2024 MARVEL DELACRUZ
Applicant returned to address corrections 10/11/2024 MARVEL DELACRUZ
Applicant returned to address corrections 3/10/2025 MARVEL DELACRUZ
Applicant returned to address corrections 3/28/2025 MARVEL DELACRUZ
Plan Check Approved 4/21/2025 MARVEL DELACRUZ
Issued 4/21/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/26/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 5/26/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 5/26/2021 JEANIE LAM
Disturb/Remove Protected Trees Cleared 6/4/2021 STEPHEN DUPREY
Sewer availability Cleared 11/16/2021 JEANETTE VONG
Low Impact Development Cleared 3/4/2022 LONDY ALVARADO
BHO/Hillside ordinance Cleared 7/15/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 8/8/2022 JEANIE LAM
Distance to fire station Cleared 9/22/2022 KURT CORRAL
Hydrant and Access approval Cleared 9/22/2022 KURT CORRAL
Miscellaneous Cleared 9/30/2022 SPENCER WEJROWSKI
Miscellaneous Cleared 9/30/2022 SPENCER WEJROWSKI
Specific Plan Cleared 9/30/2022 SPENCER WEJROWSKI
ZA Case Cleared 9/30/2022 SPENCER WEJROWSKI
ZI Cleared 9/30/2022 SPENCER WEJROWSKI
Roof/Waste drainage to street Cleared 7/2/2024 WALLIE JONG
GPI Written Notices Cleared 10/11/2024 MARVEL DELACRUZ
Grading Pre-Inspection Cleared 10/11/2024 MARVEL DELACRUZ
Miscellaneous Cleared 12/10/2024 JAZMIN ROQUE
Work Adjacent to Public Way Cleared 2/3/2025 HOK CHI CHIU
BHO/Hillside ordinance Cleared 2/4/2025 ALBERT TAM
BHO/Hillside ordinance Cleared 2/4/2025 ALBERT TAM
Permit Cleared 2/4/2025 ALBERT TAM
Encroachment in public way Cleared 2/6/2025 MARK REYES
Trees in Parkway Cleared 2/28/2025 MARVEL DELACRUZ
Building over 36-ft Cleared 3/28/2025 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 3/28/2025 CALOSHA APPROVED

Contact Information

Architect Martin,, Sandra Daniela; Lic. No.: C32516 18034 VENTURA BLVD #512      ENCINO, CA 91316
Contractor Owner-Builder       ,
Engineer Hamilton,, John O; Lic. No.: C53284 P O BOX 866      HAWTHORNE, CA 90251
Engineer Tsai,, Steve Shi-Shen; Lic. No.: GE2268 1545 VICTORY BLVD      GLENDALE, CA 91201
Geologist Termeer,, Benjamin R; Lic. No.: EG2687 1545 VICTORY BLVD 2ND FL      GLENDALE, CA 91201

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 6/18/2025 Conditional Approval CRAIG VAUGHAN
Deputy Reinf. Concrete 6/20/2025 Conditional Approval CRAIG VAUGHAN
Piling/Pier/Caisson 6/20/2025 Partial Approval ALIZAH MAYAGOITIA
Piling/Pier/Caisson 7/18/2025 Not Ready for Inspection CRAIG VAUGHAN
Piling/Pier/Caisson 7/22/2025 Partial Approval CRAIG VAUGHAN
Piling/Pier/Caisson 7/31/2025 Partial Approval CRAIG VAUGHAN
Deputy Drilled-In Anchors 10/15/2025 Conditional Approval CRAIG VAUGHAN
Footing/Foundation/Slab 10/21/2025 Partial Approval CRAIG VAUGHAN
Deputy Reinf. Concrete 10/22/2025 Conditional Approval CRAIG VAUGHAN
Footing/Foundation/Slab 11/3/2025 Partial Approval CRAIG VAUGHAN
Deputy Reinf. Concrete 11/4/2025 Conditional Approval CRAIG VAUGHAN
Footing/Foundation/Slab 11/10/2025 Partial Approval DAVID WILLIAMS
Wood Frame 12/15/2025 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 1/5/2026 Partial Approval CRAIG VAUGHAN
Green Building Rough 1/5/2026 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 1/5/2026 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 1/16/2026 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 2/13/2026 Partial Approval CRAIG VAUGHAN
Green Building Rough 2/13/2026 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 2/13/2026 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 3/17/2026 Partial Approval CRAIG VAUGHAN
HVAC-Rough 3/17/2026 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 3/17/2026 Corrections Issued CRAIG VAUGHAN
Piling/Pier/Caisson 3/17/2026 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 3/19/2026 Partial Approval CRAIG VAUGHAN
Green Building Rough 3/19/2026 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 3/19/2026 Approved CRAIG VAUGHAN
HVAC-Rough 3/23/2026 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 3/24/2026 Corrections Issued CRAIG VAUGHAN
HVAC-Rough 3/24/2026 Corrections Issued CRAIG VAUGHAN
Wood Frame 3/24/2026 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 4/9/2026 Partial Approval CRAIG VAUGHAN
HVAC-Rough 4/9/2026 Approved CRAIG VAUGHAN
Insulation 4/20/2026 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 4/20/2026 Partial Approval CRAIG VAUGHAN
Drywall Nailing 4/24/2026 Approved CRAIG VAUGHAN
Shower Pan 5/20/2026 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 6/17/2026 Approved CRAIG VAUGHAN
Deputy Reinf. Concrete 6/18/2026 Conditional Approval CRAIG VAUGHAN
Interior/Exterior Lathing 6/18/2026 Approved CRAIG VAUGHAN