2642 S MAGNOLIA AVE 90007
Certificate Information: 2642 S MAGNOLIA AVE 90007
- Application / Permit
- 21010-20000-01123
- Plan Check / Job No.
- B21VN02804
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 30'11" X 24'6" DETACHED 2-STORY ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33(C) AND (E), ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 9/30/2021
- Issuing Office
- Current Status
- CofO Issued on 11/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | RARES BODEA |
| Corrections Issued | 3/14/2021 | RARES BODEA |
| Quality Review Completed | 3/22/2021 | STEVEN KIM |
| Plan Check Approved | 9/23/2021 | RARES BODEA |
| Issued | 9/30/2021 | APPLICANT |
| CofO in Progress | 11/23/2022 | KATHRYN BUTTERWORTH |
| CofO Issued | 11/30/2022 | DEROLD HAUFF |
| Permit Finaled | 11/30/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/15/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2021 | THOMAS LANG |
| Sewer availability | Cleared | 4/15/2021 | THOMAS LANG |
| HPOZ | Cleared | 7/7/2021 | DANIEL MATA |
| Historic monument | Cleared | 7/7/2021 | DANIEL MATA |
| ZI | Cleared | 7/7/2021 | DANIEL MATA |
| Hydrant and Access approval | Cleared | 8/13/2021 | GILBERT URREA |
| ZA Case | Cleared | 8/17/2021 | JASON CHAN |
| ZI | Cleared | 8/17/2021 | JASON CHAN |
| Low Impact Development | Cleared | 8/30/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 9/2/2021 | STEVE MELGAR |
Contact Information
| Architect | Nigosian,, Michael Nickolas; Lic. No.: C35308 | 75-572 PAINTED DESERT DRIVE INDIAN WELLS, CA 92210 |
| Contractor | Owner-Builder | , |
| Engineer | Boranian,, Paul Darian; Lic. No.: S5944 | 23261 BURBANK BL WOODLAND HILLS, CA 91367 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/7/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Deputy Methane Barrier | 11/1/2021 | Approved | SABAS ALONSO |
| METHANE-Subgrade | 11/1/2021 | Approved | SABAS ALONSO |
| Deputy Methane Barrier | 11/3/2021 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 11/4/2021 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 11/10/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 11/15/2021 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 11/15/2021 | Approved | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 1/18/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| HVAC-Rough | 1/18/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 1/18/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Wood Frame | 1/18/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 1/21/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 1/21/2022 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 1/21/2022 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 1/21/2022 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 2/28/2022 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 2/28/2022 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Rough | 2/28/2022 | Approved | KATHRYN BUTTERWORTH |
| Verify Sprinkler Sign Off | 2/28/2022 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 3/3/2022 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 3/7/2022 | Corrections Issued | SCOTT FINNILA |
| Special/Order Compliance | 3/8/2022 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 3/11/2022 | Partial Approval | STUART CHAPMAN |
| Gas Test | 3/29/2022 | Approved | ADAM ESCOTO |
| Sewer | 3/29/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Sewer | 4/14/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Sewer | 4/20/2022 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 5/25/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Final | 5/25/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 5/25/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Service/Power Release | 5/25/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Drywall Nailing | 6/21/2022 | Approved | KATHRYN BUTTERWORTH |
| Final | 6/21/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Final | 6/21/2022 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 6/21/2022 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Service/Power Release | 6/21/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Smoke Detectors | 6/21/2022 | Approved | KATHRYN BUTTERWORTH |
| Final | 7/1/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 7/1/2022 | SGSOV Approved | SHAVONNE ESPINOZA |
| Service/Power Release | 7/1/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Service/Power Release | 7/8/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Service/Power Release | 8/1/2022 | Approved | KATHRYN BUTTERWORTH |
| Final | 9/8/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 10/6/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Final | 10/17/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Final | 11/9/2022 | OK to Issue CofO | KATHRYN BUTTERWORTH |