5124 N CALVIN AVE 91356
Certificate Information: 5124 N CALVIN AVE 91356
- Application / Permit
- 21010-20000-01122
- Plan Check / Job No.
- B21VN02801
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- (N) 1-STORY RECREATION ROOM W/ HALF BATHROOM & SHOWER (EXTERIOR ACCESS FOR POOL UNDER 21047-10000-00864) & TRELLIS
- Permit Issued
- Issued on 9/24/2021
- Issuing Office
- Current Status
- CofO Issued on 8/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 3/19/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 3/23/2021 | CHON CHIO KUO |
| Applicant returned to address corrections | 8/11/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 8/25/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 9/10/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 9/15/2021 | NILOOFAR MEHRAIN |
| Issued | 9/24/2021 | APPLICANT |
| CofO in Progress | 8/23/2022 | DAVID SANDOVAL |
| CofO Issued | 8/30/2022 | MICHAEL SMITH |
| Permit Finaled | 8/30/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 3/20/2021 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 3/20/2021 | NILOOFAR MEHRAIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2021 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 4/26/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 7/30/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 8/2/2021 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/12/2021 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 12/6/2021 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2022 | Not Ready for Inspection | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2022 | Partial Approval | DAVID SANDOVAL |
| ELECTRICAL-Rough | 3/18/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2022 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 3/18/2022 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 3/21/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 3/21/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 3/21/2022 | Approved | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 3/21/2022 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 3/23/2022 | Partial Approval | DAVID SANDOVAL |
| Shower Pan | 4/13/2022 | Approved | SEAN WIRCH |
| Drywall Nailing | 4/19/2022 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 4/19/2022 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Final | 8/8/2022 | Approved | DAVID SANDOVAL |
| Service/Power Release | 8/8/2022 | Approved | DAVID SANDOVAL |
| Gas Test | 8/9/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Final | 8/9/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Final | 8/9/2022 | Approved | DAVID SANDOVAL |
| Final | 8/22/2022 | OK to Issue CofO | DAVID SANDOVAL |
| Gas Test | 8/22/2022 | Approved | DAVID SANDOVAL |
| Green Building Final | 8/22/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Final | 8/22/2022 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 8/22/2022 | SGSOV Approved | DAVID SANDOVAL |
| Smoke Detectors | 8/22/2022 | Approved | DAVID SANDOVAL |