10007 N EL DORADO AVE 91331
Certificate Information: 10007 N EL DORADO AVE 91331
- Application / Permit
- 21010-20000-01119
- Plan Check / Job No.
- B21VN02785
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Carport
- Work Description
- (N) 2-CAR CARPORT (18' X 18') PER LA CITY STDS
- Permit Issued
- Issued on 9/10/2021
- Issuing Office
- Current Status
- CofO Issued on 4/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 3/14/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 6/2/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 7/28/2021 | PARISA ZAHABI |
| Issued | 9/10/2021 | APPLICANT |
| Building Plans Picked Up | 10/4/2021 | APPLICANT |
| CofO in Progress | 4/4/2022 | MICHEL ABAJAN |
| Permit Finaled | 4/6/2022 | RONALD MYRICK |
| CofO Issued | 4/6/2022 | RONALD MYRICK |
| Permit Finaled | 4/6/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 5/14/2021 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 6/4/2021 | WALTER RAMIREZ |
| Construction within easement | Cleared | 6/4/2021 | WALTER RAMIREZ |
| Hold | Cleared | 10/13/2021 | JASON SHEETS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/15/2021 | Corrections Issued | MICHEL ABAJAN |
| METHANE-Barrier | 10/15/2021 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 10/15/2021 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 11/9/2021 | Approved | MICHEL ABAJAN |
| Wood Frame | 11/18/2021 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/2/2021 | No Access for Inspection | MARK JOHNSON |
| Final | 12/2/2021 | Not Ready for Inspection | MARK JOHNSON |
| METHANE-Final | 12/2/2021 | No Access for Inspection | MARK JOHNSON |
| METHANE-Rough | 12/2/2021 | No Access for Inspection | MARK JOHNSON |
| SGSOV-Seismic Gas S/O Valve | 12/2/2021 | SGSOV Not Ready | MARK JOHNSON |
| Service/Power Release | 12/2/2021 | No Access for Inspection | MARK JOHNSON |
| Smoke Detectors | 12/2/2021 | No Access for Inspection | MARK JOHNSON |
| BUILDING-Rough-Frame | 12/7/2021 | Approved | JENNIFER RABUCHIN |
| Final | 12/7/2021 | Corrections Issued | JENNIFER RABUCHIN |
| METHANE-Final | 12/7/2021 | Approved | JENNIFER RABUCHIN |
| METHANE-Rough | 12/7/2021 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 12/7/2021 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Service/Power Release | 12/7/2021 | Not Required | JENNIFER RABUCHIN |
| Smoke Detectors | 12/7/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/4/2022 | Approved | MICHEL ABAJAN |
| Final | 4/4/2022 | OK to Issue CofO | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 4/4/2022 | SGSOV Approved | MICHEL ABAJAN |