3935 W 8TH ST 1-19 90005

Certificate Information: 3935 W 8TH ST 1-19 90005

Application / Permit
21010-20000-01110
Plan Check / Job No.
B21VN02754
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 5-STORY , 19 UNIT APT BLDGTYPE-IIIA OVER ONE LEVEL ON GRADE TYPE-IA PKG GARAGE - TOTAL 6-STORY BUILDING
Permit Issued
Issued on 12/1/2021
Issuing Office
Valley
Current Status
Issued on 12/1/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/8/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 CHON CHIO KUO
Corrections Issued 4/5/2021 CHON CHIO KUO
Quality Review Completed 4/9/2021 STEVEN KIM
Applicant returned to address corrections 7/1/2021 CHON CHIO KUO
Plan Check Approved 11/2/2021 SELLA BENYAMIN
Issued 12/1/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/17/2021 JEANIE LAM
Sewer availability Cleared 5/17/2021 JEANIE LAM
Address approval Cleared 5/18/2021 JEANIE LAM
Highway dedication Cleared 6/28/2021 CECILIO NAVARRO
ZA Case Cleared 6/30/2021 LAUREN PADICK
Permit Cleared 7/27/2021 CECILIO NAVARRO
Frnt yard landscape/Water mgmt Cleared 7/30/2021 LAUREN PADICK
Opn space landscape/Water mgmt Cleared 7/30/2021 LAUREN PADICK
Hydrant and Access approval Cleared 8/5/2021 ROBERT DUFF
Low Impact Development Cleared 10/1/2021 AMMAR ELTAWIL
Fire Marshal Fire Life Safety Cleared 10/7/2021 RONILO MULAWIN
DAS Clearance Cleared 10/12/2021 NORLITO MEDRANO
Green Code Cleared 10/19/2021 MICHAEL AYERS
Building over 36-ft Cleared 11/2/2021 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 11/2/2021 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 11/12/2021 JEANETTE VONG

Contact Information

Contractor Schon Tepler Construction, Inc; Lic. No.: 969338-B 6250 HOLLYWOOOD BLVD 10M      LOS ANGELES, CA 90028
Engineer Pirbadian,, Amir; Lic. No.: C72413 5435 BALBOA BLVD 214      ENCINO, CA 91342
Engineer Walter,, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/24/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 3/25/2022 Partial Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 4/4/2022 Partial Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 4/14/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 4/25/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 4/27/2022 Conditional Approval DARRYL ARNOLD
Deputy Reinf. Concrete 5/17/2022 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 5/17/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 5/25/2022 Conditional Approval TERRY HERR
Deputy Shotcrete 6/16/2022 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 6/16/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 6/22/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 7/22/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/25/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 8/12/2022 Not Ready for Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 8/15/2022 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 8/16/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/16/2022 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 9/26/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 9/26/2022 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 9/26/2022 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 9/26/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 10/3/2022 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 10/10/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 10/12/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 10/13/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 10/31/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 10/31/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 11/2/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 11/2/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 11/7/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 12/12/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 12/13/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 1/20/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 1/23/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 1/23/2023 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 1/23/2023 Partial Inspection EDWIN GREGORYONA
Deputy Drilled-In Anchors 6/7/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 6/21/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 6/26/2023 Not Ready for Inspection EDWIN GREGORYONA
Structural Steel Frame 6/26/2023 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 6/26/2023 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 6/26/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Steel/Welding 6/27/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 8/16/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 8/16/2023 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 8/16/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Wood Construction 8/17/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 10/2/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 10/3/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/17/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 11/17/2023 Partial Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 11/17/2023 Approved EDWIN GREGORYONA
Green Building Rough 1/29/2024 Partial Inspection EDWIN GREGORYONA
Wood Frame 1/29/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 2/29/2024 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 3/18/2024 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 3/21/2024 Partial Inspection EDWIN GREGORYONA
Wood Frame 3/21/2024 Partial Approval EDWIN GREGORYONA
Green Building Rough 5/1/2024 Approved EDWIN GREGORYONA
Wood Frame 5/1/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 6/4/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 6/7/2024 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 7/2/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 7/2/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Partial Approval EDWIN GREGORYONA
Insulation 12/3/2024 Approved EDWIN GREGORYONA
Wood Frame 12/3/2024 Approved EDWIN GREGORYONA
Wood Frame 1/14/2025 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 1/17/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 2/18/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 4/17/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 4/24/2025 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 5/2/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 5/2/2025 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 5/8/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 5/13/2025 Partial Approval MARTIN TAVITIAN
Interior/Exterior Lathing 5/13/2025 Partial Approval MARTIN TAVITIAN
Drywall Nailing 5/16/2025 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 5/16/2025 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 5/28/2025 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 6/6/2025 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 6/12/2025 Partial Approval EDWIN GREGORYONA
Special/Order Compliance 4/16/2026 Partial Approval MARTIN TAVITIAN