4103 N CAMELLIA AVE 91604
Certificate Information: 4103 N CAMELLIA AVE 91604
- Application / Permit
- 21010-20000-01100
- Plan Check / Job No.
- B21VN02722
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 38'-0" x 61'-9" TWO-STORY SINGLE FAMILY DWELLING W/ ATT. TWO-CAR GARAGE; AUTOMATIC SPRINKLER SYSTEM IS REQUIRED
- Permit Issued
- Issued on 7/7/2021
- Issuing Office
- Current Status
- CofO Issued on 6/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | SEAN SHAHMIRI |
| Corrections Issued | 3/13/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 3/16/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 3/19/2021 | APPLICANT |
| Applicant returned to address corrections | 5/4/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 5/5/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 7/2/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 7/7/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 7/7/2021 | SEAN SHAHMIRI |
| Issued | 7/7/2021 | APPLICANT |
| CofO in Progress | 6/15/2022 | DAVID MATSON |
| CofO in Progress | 6/15/2022 | DAVID MATSON |
| Permit Finaled | 6/15/2022 | MICHAEL SMITH |
| CofO Issued | 6/15/2022 | MICHAEL SMITH |
| Permit Finaled | 6/15/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/16/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2021 | LEE GUILBEAUX |
| Permit | Cleared | 3/16/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/16/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/16/2021 | LEE GUILBEAUX |
| Trees in Parkway | Cleared | 4/8/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 4/25/2021 | KURT CORRAL |
| ZI | Cleared | 4/27/2021 | STEVEN WECHSLER |
| Low Impact Development | Cleared | 6/23/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 6/23/2021 | LEE GUILBEAUX |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/23/2021 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 7/23/2021 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 7/29/2021 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2021 | Partial Approval | ARAM AVEDISIAN |
| HVAC-Rough | 9/13/2021 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 9/13/2021 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2021 | Conditional Approval | THOMAS FINNILA |
| HVAC-Rough | 9/15/2021 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 9/15/2021 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 10/14/2021 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 10/14/2021 | Approved | THOMAS FINNILA |
| Wood Frame | 10/14/2021 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/18/2021 | Conditional Approval | THOMAS FINNILA |
| Shower Pan | 10/18/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 11/3/2021 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/10/2021 | Partial Approval | JACK KARGODORIAN |
| Insulation | 11/17/2021 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/19/2021 | Partial Approval | THOMAS FINNILA |
| Drywall Nailing | 11/29/2021 | Conditional Approval | THOMAS FINNILA |
| Green Building Rough | 11/29/2021 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 1/18/2022 | Approved | MATT KELLERMAN |
| HVAC-Final | 4/6/2022 | Corrections Issued | THOMAS FINNILA |
| HVAC-Final | 4/15/2022 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 4/15/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 4/25/2022 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 5/11/2022 | Approved | DAVID MATSON |
| Final | 5/11/2022 | Corrections Issued | DAVID MATSON |
| Green Building Final | 5/11/2022 | Approved | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 5/11/2022 | SGSOV Not Ready | DAVID MATSON |
| Service/Power Release | 5/11/2022 | Not Ready for Inspection | DAVID MATSON |
| Smoke Detectors | 5/11/2022 | Approved | DAVID MATSON |
| Verify Sprinkler Sign Off | 5/11/2022 | Approved | DAVID MATSON |
| Final | 6/14/2022 | OK to Issue CofO | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 6/14/2022 | SGSOV Approved | DAVID MATSON |
| Service/Power Release | 6/14/2022 | Approved | DAVID MATSON |