6201 N YOLANDA AVE 91335
Certificate Information: 6201 N YOLANDA AVE 91335
- Application / Permit
- 21010-20000-01091
- Plan Check / Job No.
- B21VN02685
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 40' 6" X 30' 2" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 7/26/2021
- Issuing Office
- Current Status
- CofO Corrected on 1/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2021 | ALFREDO JARA |
| Corrections Issued | 3/31/2021 | ALFREDO JARA |
| Plan Check Approved | 7/2/2021 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 7/8/2021 | APPLICANT |
| Issued | 7/26/2021 | APPLICANT |
| CofO in Progress | 1/20/2023 | DAVID SCANTLIN |
| Re-Activate Permit | 1/25/2023 | JOHN JANSON |
| CofO Issued-Status Void | 1/25/2023 | JOHN JANSON |
| Permit Finaled-Status Void | 1/25/2023 | JOHN JANSON |
| Permit Finaled | 1/25/2023 | JOHN JANSON |
| CofO Corrected | 1/25/2023 | JOHN JANSON |
| Permit Finaled | 1/25/2023 | JOHN JANSON |
Permit Application Clearance Information
| ZI | Cleared | 4/1/2021 | MIGUEL GAMBOA |
| Address approval | Cleared | 4/5/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 4/6/2021 | ADRIAN CASTRO |
| ZI | Cleared | 4/8/2021 | MIGUEL GAMBOA |
| Hydrant and Access approval | Cleared | 5/24/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 6/9/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 6/9/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shamsrad,, Shima; Lic. No.: C88470 | 12300 MONTECITO RD 47 SEAL BEACH, CA 90740 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/11/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 8/11/2021 | Corrections Issued | STEVEN BACK |
| Sewer | 8/11/2021 | Approved | STEVEN BACK |
| Underground Mechanical | 8/11/2021 | Partial Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 8/26/2021 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 8/26/2021 | Approved | STEVEN BACK |
| PLUMBING-Rough | 8/26/2021 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 9/30/2021 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2021 | Partial Approval | STEVEN BACK |
| Verify Sprinkler Sign Off | 9/30/2021 | Not Ready for Inspection | STEVEN BACK |
| Deputy Wood Construction | 10/1/2021 | Conditional Approval | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 10/29/2021 | Partial Approval | SEAN HAUPT |
| ELECTRICAL-Rough | 10/29/2021 | Approved | SEAN HAUPT |
| Green Building Rough | 10/29/2021 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Rough | 10/29/2021 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 10/29/2021 | Approved | SEAN HAUPT |
| Verify Sprinkler Sign Off | 10/29/2021 | Partial Approval | SEAN HAUPT |
| Drywall Nailing | 11/10/2021 | Not Ready for Inspection | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2021 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Rough | 11/10/2021 | Approved | SEAN HAUPT |
| HVAC-Rough | 11/10/2021 | Approved | SEAN HAUPT |
| Insulation | 11/10/2021 | Not Ready for Inspection | SEAN HAUPT |
| Underground Mechanical | 11/10/2021 | Not Ready for Inspection | SEAN HAUPT |
| Insulation | 11/18/2021 | Approved | MORRIS JACKSON |
| Drywall Nailing | 11/29/2021 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 1/4/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 4/4/2022 | Approved | ROBERT GOLD |
| Final | 4/4/2022 | Corrections Issued | ROBERT GOLD |
| Green Building Final | 4/4/2022 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 4/4/2022 | SGSOV Approved | ROBERT GOLD |
| Service/Power Release | 4/4/2022 | Not Ready for Inspection | ROBERT GOLD |
| Smoke Detectors | 4/4/2022 | Approved | ROBERT GOLD |
| Verify Sprinkler Sign Off | 4/4/2022 | Not Ready for Inspection | ROBERT GOLD |
| Final | 6/24/2022 | Partial Inspection | ROBERT GOLD |
| Service/Power Release | 6/24/2022 | Partial Inspection | ROBERT GOLD |
| Final | 8/10/2022 | Corrections Issued | SEAN HAUPT |
| Service/Power Release | 8/10/2022 | Not Ready for Inspection | SEAN HAUPT |
| Final | 1/19/2023 | OK to Issue CofO | DAVID SCANTLIN |
| Service/Power Release | 1/19/2023 | Approved | DAVID SCANTLIN |