11554 W CHIQUITA ST 91604
Certificate Information: 11554 W CHIQUITA ST 91604
- Application / Permit
- 21010-20000-01032
- Plan Check / Job No.
- B21VN02493
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD W/ATT GARAGE - 1 OF 2 lot tie 55219 needs to be terminated only one linkage fee waiver allowed between 11560 & 11552-54 Chiquita St. demo permit required.
- Permit Issued
- Issued on 4/20/2022
- Issuing Office
- Current Status
- CofO Issued on 4/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | CHON CHIO KUO |
| Corrections Issued | 3/15/2021 | CHON CHIO KUO |
| Quality Review Completed | 3/18/2021 | STEVEN KIM |
| Building Plans Picked Up | 3/19/2021 | APPLICANT |
| Applicant returned to address corrections | 2/15/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 3/2/2022 | NILOOFAR MEHRAIN |
| Issued | 4/20/2022 | APPLICANT |
| CofO in Progress | 4/4/2023 | JACK KARGODORIAN |
| Permit Finaled | 4/17/2023 | MICHAEL SMITH |
| CofO Issued | 4/17/2023 | MICHAEL SMITH |
| Permit Finaled | 4/17/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/28/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 4/28/2021 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 6/4/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 11/2/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 11/9/2021 | JOSE DUARTE-DIAZ |
| ZI | Cleared | 12/22/2021 | LAUREN PADICK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 5/31/2022 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 5/31/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 5/31/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 6/10/2022 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/21/2022 | Partial Approval | THOMAS FINNILA |
| HVAC-Rough | 10/3/2022 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 10/3/2022 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/11/2022 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Rough | 10/11/2022 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 10/11/2022 | Corrections Issued | CALEB MEISTER |
| Verify Sprinkler Sign Off | 10/11/2022 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 10/21/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 10/21/2022 | Approved | JACK KARGODORIAN |
| Green Building Rough | 10/21/2022 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 10/21/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 10/21/2022 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 10/21/2022 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 10/21/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 10/28/2022 | Conditional Approval | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 10/28/2022 | Approved | JACK KARGODORIAN |
| Deputy Wood Construction | 11/1/2022 | Approved | JACK KARGODORIAN |
| Insulation | 11/3/2022 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 11/9/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Interior/Exterior Lathing | 11/9/2022 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 11/10/2022 | Approved | JACK KARGODORIAN |
| HVAC-Final | 2/22/2023 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Final | 3/6/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Final | 3/6/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 3/6/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Final | 3/9/2023 | Approved | JACK KARGODORIAN |
| Gas Test | 3/9/2023 | Approved | JACK KARGODORIAN |
| HVAC-Final | 3/9/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 3/9/2023 | Approved | JACK KARGODORIAN |
| Service/Power Release | 3/13/2023 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 3/31/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 3/31/2023 | Corrections Issued | JACK KARGODORIAN |
| Final | 3/31/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Footing/Foundation/Slab | 3/31/2023 | Approved | JACK KARGODORIAN |
| Green Building Final | 3/31/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 3/31/2023 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 3/31/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 4/4/2023 | Approved | JACK KARGODORIAN |
| Final | 4/4/2023 | OK to Issue CofO | JACK KARGODORIAN |