1666 N SAN ONOFRE DR 90272

Certificate Information: 1666 N SAN ONOFRE DR 90272

Application / Permit
21010-20000-01021
Plan Check / Job No.
B21VN02477
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
(N) 1-STORY DETACHED RECREATION ROOM (IRR 21'-4" X 15'- 9 1/2")
Permit Issued
Issued on 10/7/2021
Issuing Office
Current Status
CofO Issued on 1/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 NILOOFAR MEHRAIN
Corrections Issued 3/20/2021 NILOOFAR MEHRAIN
Quality Review Completed 3/23/2021 CHON CHIO KUO
Applicant returned to address corrections 6/9/2021 NILOOFAR MEHRAIN
Plan Check Approved 7/7/2021 NILOOFAR MEHRAIN
Issued 10/7/2021 APPLICANT
CofO in Progress 12/29/2022 JUAN VALENZUELA
Permit Finaled 1/3/2023 DANIEL ORRANTE
CofO Issued 1/3/2023 DANIEL ORRANTE
Permit Finaled 1/3/2023 DANIEL ORRANTE

Permit Application Clearance Information

ZA Case Cleared 6/10/2021 LAUREN PADICK
Grading Pre-Inspection Cleared 6/15/2021 BRIAN MILLER
Sewer availability Cleared 6/18/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 6/29/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/20/2021 DINAH GARIN
Miscellaneous Cleared 10/5/2021 JENSON LEE

Contact Information

Contractor Sound Structures Inc; Lic. No.: 923028-B 21017 HILLSIDE DRIVE      TOPANGA, CA 90290
Engineer Koma,, Shahram Javadi; Lic. No.: C69497 23241 VENTURA BLVD 300      WOODLAND HILLS, CA 91364

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 10/13/2021 Corrections Issued JUAN VALENZUELA
Pre-Inspection 10/13/2021 Partial Inspection JUAN VALENZUELA
Deputy Reinf. Concrete 10/14/2021 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 10/19/2021 Partial Approval JUAN VALENZUELA
Piling/Pier/Caisson 10/19/2021 Partial Approval JUAN VALENZUELA
Deputy Other (see comments) 10/22/2021 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 11/29/2021 Partial Approval BRENDAN LOONEY
Masonry Wall/Backfill 12/10/2021 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 1/6/2022 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 2/11/2022 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 2/24/2022 Approved JUAN VALENZUELA
Green Building Rough 2/24/2022 Not Ready for Inspection JUAN VALENZUELA
Verify Sprinkler Sign Off 2/24/2022 Corrections Issued JUAN VALENZUELA
Interior/Exterior Lathing 2/28/2022 Approved JOHN KIDWELL
ELECTRICAL-Rough 3/16/2022 Approved JUAN VALENZUELA
HVAC-Rough 3/16/2022 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 3/21/2022 Corrections Issued JUAN VALENZUELA
Green Building Rough 3/21/2022 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 3/21/2022 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 4/1/2022 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 4/1/2022 Approved JUAN VALENZUELA
Drywall Nailing 4/6/2022 Approved JOHN KIDWELL
Green Building Final 8/11/2022 Approved JUAN VALENZUELA
Smoke Detectors 8/11/2022 Approved JUAN VALENZUELA
ELECTRICAL-Final 10/26/2022 Approved JUAN VALENZUELA
PLUMBING-Final 10/26/2022 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 10/26/2022 SGSOV Approved JUAN VALENZUELA
Service/Power Release 10/26/2022 Approved JUAN VALENZUELA
Final 12/29/2022 OK to Issue CofO JUAN VALENZUELA