13355 W REEDLEY ST 91402

Certificate Information: 13355 W REEDLEY ST 91402

Application / Permit
21010-20000-01011
Plan Check / Job No.
B21VN02457
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 48'-2" X 25'-0", 1,190 SQ. FT. DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK SHALL CONFORM TO THE WFPP.
Permit Issued
Issued on 10/28/2021
Issuing Office
Current Status
CofO Issued on 9/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 COLIN LOREDO
Corrections Issued 3/30/2021 COLIN LOREDO
Quality Review Completed 4/13/2021 OMID HEDAYAT
Building Plans Picked Up 6/21/2021 APPLICANT
Applicant returned to address corrections 9/30/2021 COLIN LOREDO
Plan Check Approved 10/25/2021 COLIN LOREDO
Issued 10/28/2021 APPLICANT
CofO in Progress 8/19/2022 GREGG CUMMINGS
Permit Finaled 9/3/2022 MICHAEL SMITH
CofO Issued 9/3/2022 MICHAEL SMITH
Permit Finaled 9/3/2022 MICHAEL SMITH

Permit Application Clearance Information

Hydrant and Access approval Cleared 5/18/2021 GILBERT URREA
"T" removal Cleared 6/22/2021 DANG NGUYEN
ZA Case Cleared 6/22/2021 DANG NGUYEN
Low Impact Development Cleared 8/14/2021 MARTIN FRAGOSO
Address approval Cleared 8/17/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 8/18/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 8/18/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 8/23/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/24/2021 Approved MICHEL ABAJAN
Underground Mechanical 11/24/2021 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 11/29/2021 Partial Approval GREGG CUMMINGS
Footing/Foundation/Slab 12/3/2021 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 12/22/2021 Partial Approval CALEB MEISTER
Wood Frame 12/22/2021 Not Ready for Inspection CALEB MEISTER
ELECTRICAL-Rough 1/13/2022 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 1/13/2022 Partial Approval GREGG CUMMINGS
HVAC-Rough 1/13/2022 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 1/13/2022 Not Ready for Inspection GREGG CUMMINGS
Wood Frame 1/13/2022 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 1/20/2022 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 1/20/2022 Approved GREGG CUMMINGS
Green Building Rough 1/20/2022 Approved GREGG CUMMINGS
HVAC-Rough 1/20/2022 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 1/20/2022 Approved GREGG CUMMINGS
Verify Sprinkler Sign Off 1/20/2022 Approved GREGG CUMMINGS
Wood Frame 1/20/2022 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 1/25/2022 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 1/25/2022 Partial Approval GREGG CUMMINGS
HVAC-Rough 1/25/2022 Not Ready for Inspection GREGG CUMMINGS
Interior/Exterior Lathing 1/25/2022 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 1/27/2022 Approved GREGG CUMMINGS
HVAC-Rough 1/27/2022 Approved GREGG CUMMINGS
Insulation 1/31/2022 Conditional Approval WILLIAM WREN
Insulation 2/3/2022 Approved WILLIAM WREN
Sewer 2/3/2022 Approved WILLIAM WREN
Shower Pan 2/3/2022 Approved WILLIAM WREN
Underground Mechanical 2/3/2022 Approved WILLIAM WREN
Drywall Nailing 2/11/2022 Approved WILLIAM WREN
Interior/Exterior Lathing 2/11/2022 Approved WILLIAM WREN
ELECTRICAL-Final 4/26/2022 Not Ready for Inspection GREGG CUMMINGS
Final 4/26/2022 Corrections Issued GREGG CUMMINGS
Green Building Final 4/26/2022 Approved GREGG CUMMINGS
HVAC-Final 4/26/2022 Approved GREGG CUMMINGS
PLUMBING-Final 4/26/2022 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 4/26/2022 SGSOV Approved GREGG CUMMINGS
Service/Power Release 4/26/2022 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 4/26/2022 Approved GREGG CUMMINGS
Final 8/10/2022 Corrections Issued GREGG CUMMINGS
Service/Power Release 8/10/2022 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Final 8/16/2022 Not Ready for Inspection GREGG CUMMINGS
Final 8/16/2022 Corrections Issued GREGG CUMMINGS
PLUMBING-Final 8/16/2022 Not Ready for Inspection GREGG CUMMINGS
Service/Power Release 8/16/2022 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Final 8/19/2022 Approved GREGG CUMMINGS
Final 8/19/2022 OK to Issue CofO GREGG CUMMINGS
PLUMBING-Final 8/19/2022 Approved GREGG CUMMINGS
Service/Power Release 8/19/2022 Approved GREGG CUMMINGS