22935 W DOLOROSA ST 91367
Certificate Information: 22935 W DOLOROSA ST 91367
- Application / Permit
- 21010-20000-01005
- Plan Check / Job No.
- B21VN02438
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORRY DWELLING UNIT (31'-9"X40'-0") PER LAMC 12.22 A.33(c) and (d) , ALL WORK PER WFPP FIRE SPRINKLER NFPA 13D
- Permit Issued
- Issued on 10/22/2021
- Issuing Office
- Current Status
- CofO Issued on 5/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 3/27/2021 | MOHAMMAD ESMAILI |
| Quality Review Completed | 4/13/2021 | OMID HEDAYAT |
| Plan Check Approved | 10/22/2021 | MOHAMMAD ESMAILI |
| Issued | 10/22/2021 | APPLICANT |
| CofO in Progress | 12/18/2023 | TROY SANDERS |
| Permit Finaled | 5/28/2024 | JOHN JANSON |
| CofO Issued | 5/28/2024 | JOHN JANSON |
| Permit Finaled | 5/28/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2021 | CARLOS AGUILERA |
| Certificate of Compliance | Cleared | 6/10/2021 | NOAH MCCOY |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/14/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 9/11/2021 | JOHN CONNEALLY |
| Roof/Waste drainage to street | Cleared | 9/23/2021 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 10/22/2021 | MOHAMMAD ESMAILI |
| Grading Pre-Inspection | Cleared | 10/22/2021 | MOHAMMAD ESMAILI |
| Low Impact Development | Cleared | 10/22/2021 | SUNG JOON WON |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/3/2021 | Approved | TROY SANDERS |
| Sewer | 11/3/2021 | Approved | TROY SANDERS |
| Insulation | 11/29/2021 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 11/29/2021 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 12/17/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2021 | Approved | DAVID SCANTLIN |
| Green Building Rough | 12/17/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 12/17/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Interior/Exterior Lathing | 12/22/2021 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 6/2/2022 | Not Ready for Inspection | TROY SANDERS |
| ELECTRICAL-Rough | 6/2/2022 | Approved | TROY SANDERS |
| Green Building Rough | 6/2/2022 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Rough | 6/2/2022 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 6/2/2022 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 6/2/2022 | Corrections Issued | TROY SANDERS |
| Rough-Elec/Plmb/HVAC | 7/13/2022 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 7/13/2022 | Approved | TROY SANDERS |
| Insulation | 7/27/2022 | Not Ready for Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 8/11/2022 | Approved | TROY SANDERS |
| Green Building Rough | 8/11/2022 | Approved | TROY SANDERS |
| Insulation | 8/11/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 8/29/2022 | Approved | MORRIS JACKSON |
| Shower Pan | 8/29/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 9/6/2022 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Final | 5/15/2023 | Approved | TROY SANDERS |
| Final | 5/15/2023 | Corrections Issued | TROY SANDERS |
| Footing/Foundation/Slab | 5/15/2023 | Approved | TROY SANDERS |
| Green Building Final | 5/15/2023 | Approved | TROY SANDERS |
| HVAC-Final | 5/15/2023 | Approved | TROY SANDERS |
| PLUMBING-Final | 5/15/2023 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/15/2023 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 5/15/2023 | Not Ready for Inspection | TROY SANDERS |
| Smoke Detectors | 5/15/2023 | Approved | TROY SANDERS |
| Final | 12/15/2023 | OK to Issue CofO | TROY SANDERS |
| Service/Power Release | 12/15/2023 | Approved | TROY SANDERS |