1141 S FRESNO ST 90063
Certificate Information: 1141 S FRESNO ST 90063
- Application / Permit
- 21010-20000-00947
- Plan Check / Job No.
- B21VN02349
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (15'-0"x 21'-6") DETACHED 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 6/13/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | TROY DEGUZMAN |
| Corrections Issued | 3/20/2021 | TROY DEGUZMAN |
| Quality Review Completed | 4/1/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 9/23/2021 | APPLICANT |
| Plan Check Approved | 6/7/2022 | TROY DEGUZMAN |
| Issued | 6/13/2022 | APPLICANT |
| CofO in Progress | 9/5/2025 | FREDDIE RIVERA |
| CofO Issued | 9/8/2025 | DEROLD HAUFF |
| Permit Finaled | 9/8/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 3/31/2021 | TROY DEGUZMAN |
| ZI | Cleared | 5/27/2021 | LAUREN PADICK |
| Address approval | Cleared | 7/13/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 7/13/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/29/2022 | JEANIE LAM |
| Sewer availability | Cleared | 3/30/2022 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 4/4/2022 | ALEXANDER ANDREWS |
| Hydrant and Access approval | Cleared | 4/26/2022 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manoukian,, Krikor Kerop; Lic. No.: C87010 | 2310 W MAGNOLIA BLVD STE A BURBANK, CA 91506 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/26/2023 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 7/25/2023 | Conditional Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2023 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 2/22/2024 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 2/22/2024 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2024 | Partial Approval | FREDDIE RIVERA |
| Green Building Rough | 3/19/2024 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Rough | 3/19/2024 | Partial Inspection | FREDDIE RIVERA |
| MERV13>=Rough | 3/19/2024 | Partial Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 3/19/2024 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 3/28/2024 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 3/28/2024 | Approved | JOSEPH MCGARRY |
| Insulation | 4/4/2024 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 4/25/2024 | Approved | FREDDIE RIVERA |
| Green Building Rough | 4/25/2024 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 4/25/2024 | Partial Approval | FREDDIE RIVERA |
| Interior/Exterior Lathing | 5/30/2024 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 2/14/2025 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 2/14/2025 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 2/14/2025 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Final | 2/14/2025 | Not Ready for Inspection | FREDDIE RIVERA |
| MERV13>=Final | 2/14/2025 | Not Ready for Inspection | FREDDIE RIVERA |
| MERV13>=Rough | 2/14/2025 | Not Ready for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 2/14/2025 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 2/14/2025 | Not Ready for Inspection | FREDDIE RIVERA |
| Smoke Detectors | 2/14/2025 | Not Ready for Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 2/14/2025 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Final | 5/30/2025 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 7/11/2025 | Approved | FREDDIE RIVERA |
| Final | 7/11/2025 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 7/11/2025 | Approved | FREDDIE RIVERA |
| Green Building Final | 7/11/2025 | Partial Inspection | FREDDIE RIVERA |
| MERV13>=Final | 7/11/2025 | Partial Inspection | FREDDIE RIVERA |
| MERV13>=Rough | 7/11/2025 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 7/11/2025 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 7/11/2025 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 7/11/2025 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 7/11/2025 | Approved | FREDDIE RIVERA |
| Green Building Final | 7/22/2025 | Approved | FREDDIE RIVERA |
| Final | 7/24/2025 | OK to Issue CofO | FREDDIE RIVERA |
| MERV13>=Final | 7/24/2025 | Approved | FREDDIE RIVERA |
| Service/Power Release | 7/24/2025 | Approved | FREDDIE RIVERA |