10141 N JOVITA AVE 91311

Certificate Information: 10141 N JOVITA AVE 91311

Application / Permit
21010-20000-00943
Plan Check / Job No.
B21VN02333
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 38'X 11'-2" DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)1, (d)1, and (g) ALL WORK PER WFPP
Permit Issued
Issued on 10/26/2021
Issuing Office
Current Status
CofO Issued on 10/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/26/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 3/19/2021 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 4/8/2021 OMID HEDAYAT
Plan Check Approved 10/25/2021 SEWADA ZADOORAN MILAGARDI
Issued 10/26/2021 APPLICANT
CofO in Progress 10/17/2023 DAVID SCANTLIN
Permit Finaled 10/17/2023 JOHN JANSON
CofO Issued 10/17/2023 JOHN JANSON
Permit Finaled 10/17/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/19/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/23/2021 GABRIEL ROBLES
Sewer availability Cleared 8/23/2021 GABRIEL ROBLES
Low Impact Development Cleared 10/6/2021 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 10/20/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
DAVID SCANTLIN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/14/2021 Approved JEFFREY PARD
Footing/Foundation/Slab 12/16/2021 Not Ready for Inspection JEFFREY PARD
Footing/Foundation/Slab 1/4/2022 Approved JEFFREY PARD
PLUMBING-Rough 1/27/2022 Partial Approval JEFFREY PARD
Sewer 1/27/2022 Approved JEFFREY PARD
Wood Frame 1/27/2022 Partial Approval JEFFREY PARD
ELECTRICAL-Rough 2/7/2022 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 2/7/2022 Approved JEFFREY PARD
Gas Test 2/7/2022 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 2/28/2022 Approved JEFFREY PARD
BUILDING-Rough-Frame 3/7/2022 Partial Approval JEFFREY PARD
ELECTRICAL-Rough 3/7/2022 Corrections Issued JEFFREY PARD
Green Building Rough 3/7/2022 Not Ready for Inspection JEFFREY PARD
Rough-Elec/Plmb/HVAC 3/7/2022 Partial Approval JEFFREY PARD
Verify Sprinkler Sign Off 3/7/2022 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 3/10/2022 Approved JEFFREY PARD
Green Building Rough 3/17/2022 Approved JUSTIN HAWLEY
Insulation 3/17/2022 Conditional Approval JUSTIN HAWLEY
Interior/Exterior Lathing 3/17/2022 Approved JUSTIN HAWLEY
Shower Pan 3/17/2022 Approved JUSTIN HAWLEY
Drywall Nailing 3/24/2022 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 4/21/2022 Approved JEFFREY PARD
Final 4/21/2022 Corrections Issued JEFFREY PARD
Green Building Final 4/21/2022 Corrections Issued JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 4/21/2022 SGSOV Approved JEFFREY PARD
Service/Power Release 4/21/2022 Not Required JEFFREY PARD
Smoke Detectors 4/21/2022 Approved JEFFREY PARD
Final 5/17/2022 Not Ready for Inspection JEFFREY PARD
Green Building Final 5/17/2022 Not Ready for Inspection JEFFREY PARD
Green Building Final 8/15/2023 Not Ready for Inspection JOHN KIDWELL
Special/Order Compliance 8/15/2023 Partial Inspection JEFFREY HARTLINE
Final 10/16/2023 OK to Issue CofO DAVID SCANTLIN
Green Building Final 10/16/2023 Approved DAVID SCANTLIN