4017 N DEERVALE DR 91403

Certificate Information: 4017 N DEERVALE DR 91403

Application / Permit
21010-20000-00920
Plan Check / Job No.
B21VN02267
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 28'-0" X 23'-4", 1,146 SQ. FT. 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) WITH PILES. NFPA 13R FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING. (TYPE VA CONSTRUCTION AND NFPA 13R FIRE SPRINKLERS REQUIRED PER LAFD)
Permit Issued
Issued on 2/10/2022
Issuing Office
Current Status
CofO Issued on 6/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/26/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 COLIN LOREDO
Corrections Issued 3/23/2021 COLIN LOREDO
Quality Review Completed 4/1/2021 OMID HEDAYAT
Applicant returned to address corrections 5/26/2021 COLIN LOREDO
Applicant returned to address corrections 6/2/2021 COLIN LOREDO
Applicant returned to address corrections 10/25/2021 COLIN LOREDO
Plan Check Approved 12/29/2021 COLIN LOREDO
Issued 2/10/2022 APPLICANT
CofO in Progress 6/21/2023 JOHN COLEMAN
Permit Finaled 6/23/2023 MICHAEL SMITH
CofO Issued 6/23/2023 MICHAEL SMITH
Permit Finaled 6/23/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/23/2021 JOHN TRIANTAFYLLOS
BHO/Hillside ordinance Cleared 3/23/2021 JOHN TRIANTAFYLLOS
BHO/Hillside ordinance Cleared 3/23/2021 JOHN TRIANTAFYLLOS
BHO/Hillside ordinance Cleared 3/23/2021 JOHN TRIANTAFYLLOS
BHO/Hillside ordinance Cleared 3/23/2021 JOHN TRIANTAFYLLOS
BHO/Hillside ordinance Cleared 3/23/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/24/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/24/2021 JOHN TRIANTAFYLLOS
ZA Case Cleared 3/30/2021 MIGUEL GAMBOA
Construction near power lines Cleared 7/29/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 8/16/2021 MATTHEW CRAIG
GPI Written Notices Cleared 12/29/2021 COLIN LOREDO
Grading Pre-Inspection Cleared 12/29/2021 COLIN LOREDO
Low Impact Development Cleared 12/29/2021 LONDY ALVARADO
Roof/Waste drainage to street Cleared 12/30/2021 ABDULLAH SADOZAI

Contact Information

Contractor Structa Ii; Lic. No.: 999353-B 16030 VENTURA BLVD SUITE 430      ENCINO, CA 91436
Engineer Judd,, Shane Dennis; Lic. No.: C70991 17 E HIGH ST STE A      MOORPARK, CA 93021

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/29/2022 Partial Approval JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 4/26/2022 Partial Approval JACK KARGODORIAN
Piling/Pier/Caisson 4/26/2022 Partial Approval JACK KARGODORIAN
Piling/Pier/Caisson 4/29/2022 Corrections Issued JACK KARGODORIAN
Piling/Pier/Caisson 5/4/2022 Partial Approval CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 6/14/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 6/14/2022 Partial Approval JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 6/24/2022 Partial Approval JACK KARGODORIAN
Masonry Wall/Backfill 7/18/2022 Partial Approval MATT KELLERMAN
Masonry Wall/Backfill 7/26/2022 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 8/10/2022 Partial Approval JACK KARGODORIAN
Green Building Rough 8/10/2022 Not Ready for Inspection JACK KARGODORIAN
Pre-Inspection 8/10/2022 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 8/25/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 9/1/2022 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 9/1/2022 Not Ready for Inspection JACK KARGODORIAN
HVAC-Rough 9/1/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 9/1/2022 Approved JACK KARGODORIAN
Shower Pan 9/16/2022 Approved JACK KARGODORIAN
Insulation 9/21/2022 Approved JACK KARGODORIAN
Interior/Exterior Lathing 9/21/2022 Partial Approval JACK KARGODORIAN
Insulation 9/28/2022 Partial Approval MATTHEW NELSON
Rough-Elec/Plmb/HVAC 9/28/2022 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 10/6/2022 Corrections Issued JACK KARGODORIAN
Deputy Wood Construction 10/12/2022 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 10/18/2022 Approved THOMAS FINNILA
Interior/Exterior Lathing 10/18/2022 Partial Approval THOMAS FINNILA
Drywall Nailing 10/28/2022 Approved THOMAS FINNILA
Green Building Rough 10/28/2022 Approved THOMAS FINNILA
Interior/Exterior Lathing 10/28/2022 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 3/8/2023 Partial Inspection JOHN COLEMAN
ELECTRICAL-Final 3/8/2023 Approved JOHN COLEMAN
Final 3/8/2023 Not Ready for Inspection JOHN COLEMAN
Footing/Foundation/Slab 3/8/2023 Approved JOHN COLEMAN
Green Building Final 3/8/2023 Corrections Issued JOHN COLEMAN
HVAC-Final 3/8/2023 Approved JOHN COLEMAN
PLUMBING-Final 3/8/2023 Approved JOHN COLEMAN
Reinforced Concrete Frame 3/8/2023 Partial Inspection JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 3/8/2023 SGSOV Approved JOHN COLEMAN
Service/Power Release 3/8/2023 Not Ready for Inspection JOHN COLEMAN
Smoke Detectors 3/8/2023 Approved JOHN COLEMAN
Verify Sprinkler Sign Off 3/8/2023 Not Ready for Inspection JOHN COLEMAN
BUILDING-Rough-Frame 6/21/2023 Approved JOHN COLEMAN
Final 6/21/2023 OK to Issue CofO JOHN COLEMAN
Green Building Final 6/21/2023 Approved JOHN COLEMAN
Reinforced Concrete Frame 6/21/2023 Approved JOHN COLEMAN
Service/Power Release 6/21/2023 Approved JOHN COLEMAN
Verify Sprinkler Sign Off 6/21/2023 Approved JOHN COLEMAN