4952 N VANALDEN AVE 91356
Certificate Information: 4952 N VANALDEN AVE 91356
- Application / Permit
- 21010-20000-00917
- Plan Check / Job No.
- B21VN02242
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY 89'-10" X 100-10", 8,220 SQ. FT. IRREGULAR SHAPED SINGLE FAMILY DWELLING W/ATT. GARAGE AND COVERED PATIO AREA . NFPA 13R FIRE SPRINKLERS REQUIRED THROUGHOUT PER LAFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/15/2022
- Issuing Office
- Valley
- Current Status
- Issued on 8/15/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | COLIN LOREDO |
| Corrections Issued | 3/25/2021 | COLIN LOREDO |
| Quality Review Completed | 4/13/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 5/24/2021 | COLIN LOREDO |
| Applicant returned to address corrections | 8/16/2021 | COLIN LOREDO |
| Plan Check Approved | 7/28/2022 | COLIN LOREDO |
| Issued | 8/15/2022 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/11/2021 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 5/11/2021 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 5/11/2021 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 5/11/2021 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 5/11/2021 | LEE GUILBEAUX |
| ZA Case | Cleared | 5/12/2021 | LAUREN PADICK |
| ZA Case | Cleared | 5/12/2021 | LAUREN PADICK |
| Certificate of Compliance | Cleared | 5/25/2021 | MARC WOERSCHING |
| Miscellaneous | Cleared | 5/25/2021 | MARC WOERSCHING |
| Miscellaneous | Cleared | 5/25/2021 | MARC WOERSCHING |
| Eng Process Fee Ord 176,300 | Cleared | 6/22/2021 | ROSE MARIE SMITH |
| Sewer availability | Cleared | 9/30/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 11/15/2021 | TA ANH |
| Distance to fire station | Cleared | 6/16/2022 | GILBERT URREA |
| Hydrant and Access approval | Cleared | 6/25/2022 | GILBERT URREA |
| Roof/Waste drainage to street | Cleared | 7/22/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Oruncakciel,, Sayat; Lic. No.: C77182 | 15445 VENTURA BLVD 25 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 7/5/2023 | Partial Approval | SEAN HAUPT |
| Pre-Inspection | 1/22/2024 | Approved | SEAN HAUPT |
| Deputy Grading | 1/26/2024 | Conditional Approval | MORRIS JACKSON |
| Deputy Grading | 1/29/2024 | Approved | SEAN HAUPT |
| Deputy Grading | 1/30/2024 | Approved | ROBERT PINA |
| Deputy Grading | 1/30/2024 | Partial Approval | JOHN KIDWELL |
| Deputy Grading | 1/31/2024 | Approved | ROBERT PINA |
| Deputy Grading | 2/1/2024 | No Access for Inspection | ROBERT PINA |
| Deputy Grading | 2/2/2024 | No Access for Inspection | ROBERT PINA |
| Deputy Grading | 2/7/2024 | Approved | ROBERT PINA |
| Deputy Grading | 2/12/2024 | Partial Approval | JOHN KIDWELL |
| Deputy Grading | 2/13/2024 | Partial Approval | JOHN KIDWELL |
| Deputy Grading | 2/14/2024 | Partial Approval | JOHN KIDWELL |
| Deputy Grading | 2/15/2024 | Partial Approval | JOHN KIDWELL |
| Deputy Grading | 2/16/2024 | Partial Approval | JOHN KIDWELL |
| Piling/Pier/Caisson | 2/29/2024 | Partial Approval | JOHN KIDWELL |
| Deputy Reinf. Concrete | 3/4/2024 | Partial Approval | JOHN KIDWELL |
| Piling/Pier/Caisson | 3/22/2024 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 6/17/2024 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 6/17/2024 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 6/21/2024 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 6/26/2024 | Corrections Issued | JOHN KIDWELL |
| Deputy Reinf. Concrete | 6/28/2024 | Conditional Approval | MORRIS JACKSON |
| Footing/Foundation/Slab | 8/1/2024 | Approved | JOHN KIDWELL |
| Deputy Reinf. Concrete | 8/7/2024 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2024 | Corrections Issued | JOHN KIDWELL |
| Sewer | 12/2/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Gas Test | 12/16/2024 | Partial Approval | SEAN WIRCH |
| PLUMBING-Rough | 12/20/2024 | Approved | JOHN KIDWELL |
| Insulation | 2/18/2025 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 4/28/2025 | Approved | JOHN KIDWELL |
| Green Building Rough | 4/28/2025 | Approved | JOHN KIDWELL |
| Rough-Elec/Plmb/HVAC | 4/28/2025 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 4/28/2025 | Approved | JOHN KIDWELL |
| Insulation | 5/22/2025 | Approved | JOHN KIDWELL |
| Drywall Nailing | 6/9/2025 | Approved | JOHN COLEMAN |
| Shower Pan | 6/9/2025 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 6/23/2025 | Partial Approval | JOHN KIDWELL |
| Sewer | 8/11/2025 | Partial Approval | MORRIS JACKSON |
| ELECTRICAL-Rough | 8/14/2025 | Approved | JOHN KIDWELL |
| Gas Test | 10/9/2025 | Approved | JOHN KIDWELL |
| Gas Test | 3/6/2026 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 3/6/2026 | SGSOV Approved | JOHN KIDWELL |
| PLUMBING-Final | 3/26/2026 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 4/1/2026 | Approved | JOHN KIDWELL |
| HVAC-Final | 4/1/2026 | Approved | JOHN KIDWELL |
| Service/Power Release | 4/1/2026 | Approved | JOHN KIDWELL |