15823 W WOODVALE ROAD 91436

Certificate Information: 15823 W WOODVALE ROAD 91436

Application / Permit
21010-20000-00916
Plan Check / Job No.
B21VN02239
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 41'-0" X 21'-0" , 785 SQ. FT. ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). NFPA 13-D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 7/21/2021
Issuing Office
Valley
Current Status
CofO Issued on 7/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 COLIN LOREDO
Corrections Issued 3/9/2021 COLIN LOREDO
Quality Review Completed 3/9/2021 OMID HEDAYAT
Building Plans Picked Up 3/16/2021 APPLICANT
Applicant returned to address corrections 6/17/2021 COLIN LOREDO
Applicant returned to address corrections 6/24/2021 COLIN LOREDO
Plan Check Approved 7/21/2021 COLIN LOREDO
Issued 7/21/2021 APPLICANT
CofO in Progress 7/1/2022 VINCENT HANLEY
Permit Finaled 7/21/2022 MICHAEL SMITH
CofO Issued 7/21/2022 MICHAEL SMITH
Permit Finaled 7/21/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/10/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/12/2021 ADRIAN CASTRO
Sewer availability Cleared 3/12/2021 ADRIAN CASTRO
Hydrant and Access approval Cleared 4/25/2021 MATTHEW CRAIG
Low Impact Development Cleared 6/8/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 6/9/2021 DAGOVERTO GUERRERO
GPI Written Notices Cleared 7/21/2021 COLIN LOREDO
Grading Pre-Inspection Cleared 7/21/2021 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/17/2021 Approved RONALD COWAN
Footing/Foundation/Slab 9/17/2021 Approved RONALD COWAN
Underground Mechanical 9/17/2021 Approved RONALD COWAN
Excavation/Setback/Form/Re-Bar 9/27/2021 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 11/24/2021 Partial Approval ROBERT GOLD
PLUMBING-Rough 1/14/2022 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 1/19/2022 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Rough 1/19/2022 Approved DAVID SANDOVAL
Green Building Rough 1/19/2022 Not Ready for Inspection DAVID SANDOVAL
HVAC-Rough 1/19/2022 Approved DAVID SANDOVAL
Verify Sprinkler Sign Off 1/19/2022 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 1/27/2022 Approved DAVID SANDOVAL
Green Building Rough 1/27/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 1/27/2022 Partial Approval DAVID SANDOVAL
Insulation 2/1/2022 Approved KRISTEN CAUSEY
Drywall Nailing 2/7/2022 Not Ready for Inspection JUSTIN HAWLEY
Shower Pan 2/7/2022 Approved JUSTIN HAWLEY
Drywall Nailing 2/10/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 2/10/2022 Approved JAVIER RAMOS JR
Underground Mechanical 4/7/2022 Partial Approval VINCENT HANLEY
ELECTRICAL-Final 6/22/2022 Approved VINCENT HANLEY
HVAC-Final 6/22/2022 Approved VINCENT HANLEY
PLUMBING-Final 6/22/2022 Approved VINCENT HANLEY
Service/Power Release 6/22/2022 Not Ready for Inspection VINCENT HANLEY
Final 6/29/2022 Corrections Issued VINCENT HANLEY
Green Building Final 6/29/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 6/29/2022 SGSOV Approved VINCENT HANLEY
Service/Power Release 6/29/2022 Not Ready for Inspection VINCENT HANLEY
Smoke Detectors 6/29/2022 Approved VINCENT HANLEY
Final 7/1/2022 OK to Issue CofO VINCENT HANLEY
Service/Power Release 7/1/2022 Approved VINCENT HANLEY