1268 N AMALFI DR 90272

Certificate Information: 1268 N AMALFI DR 90272

Application / Permit
21010-20000-00908
Plan Check / Job No.
B21VN02230
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW DETACHED 11' X 40' 8" OPEN TRELLIS. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 4/9/2021
Issuing Office
Current Status
CofO Issued on 12/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2021 APPLICANT
Assigned to Plan Check Engineer 3/5/2021 GURUNATH NESARAJAH
Corrections Issued 3/24/2021 GURUNATH NESARAJAH
Plan Check Approved 4/8/2021 GURUNATH NESARAJAH
Issued 4/9/2021 APPLICANT
Building Plans Picked Up 4/13/2021 APPLICANT
CofO in Progress 11/15/2021 ANDREW NAVE
CofO in Progress 11/15/2021 ANDREW NAVE
Permit Finaled 12/4/2021 DANIEL ORRANTE
CofO Issued 12/4/2021 DANIEL ORRANTE
Permit Finaled 12/4/2021 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/5/2021 KIRK LINKLATER

Contact Information

Contractor G D S Designs Inc; Lic. No.: 812498-C27 6547 HOMEWOOD AVE      LOS ANGELES, CA 900287820
Engineer Kazemi,, Milad; Lic. No.: C92143 6250 CANOGA AVE #525      WOODLAND HILLS, CA 91367

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/28/2021 Corrections Issued KENNETH NAGLE
Footing/Foundation/Slab 5/7/2021 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 6/1/2021 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 6/10/2021 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 7/28/2021 Corrections Issued JUAN VALENZUELA
Final 7/28/2021 Not Ready for Inspection JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 7/28/2021 SGSOV Not Ready JUAN VALENZUELA
Verify Sprinkler Sign Off 7/28/2021 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 11/4/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Final 11/4/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 11/4/2021 SGSOV Approved GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 11/4/2021 Approved GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 11/15/2021 Approved ANDREW NAVE
Final 11/15/2021 OK to Issue CofO ANDREW NAVE