755 N NAPOLI DR 90272
Certificate Information: 755 N NAPOLI DR 90272
- Application / Permit
- 21010-20000-00898
- Plan Check / Job No.
- B21VN02188
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD WITH BASEMENT AND ATTACHED 2-CAR GARAGE (76'-0"x74'-11") FIRE SPRINKLER NFPA-13D
- Permit Issued
- Issued on 7/2/2021
- Issuing Office
- Current Status
- CofO Issued on 11/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 3/11/2021 | MOHAMMAD ESMAILI |
| Quality Review Completed | 3/12/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 3/17/2021 | APPLICANT |
| Applicant returned to address corrections | 6/21/2021 | MOHAMMAD ESMAILI |
| Plan Check Approved | 6/21/2021 | MOHAMMAD ESMAILI |
| Issued | 7/2/2021 | APPLICANT |
| CofO in Progress | 11/8/2023 | ARAM AVEDISIAN |
| Permit Finaled | 11/20/2023 | DANIEL ORRANTE |
| CofO Issued | 11/20/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/20/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 3/22/2021 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 3/22/2021 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 3/22/2021 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 3/22/2021 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 3/22/2021 | CATHERINE ADROVER |
| Permit | Cleared | 3/22/2021 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2021 | CATHERINE ADROVER |
| Sewer availability | Cleared | 3/23/2021 | CATHERINE ADROVER |
| Trees in Parkway | Cleared | 4/15/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 4/25/2021 | ROBERT DUFF |
| Fire Marshal Fire Life Safety | Cleared | 5/7/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 6/11/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 6/18/2021 | DINAH GARIN |
| Excavation more than 5-ft deep | Cleared | 6/21/2021 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 6/21/2021 | MOHAMMAD ESMAILI |
| Grading Pre-Inspection | Cleared | 6/21/2021 | MOHAMMAD ESMAILI |
Contact Information
| Contractor | Williams Craig R Construction Inc; Lic. No.: 479539-B | 9100 WILSHIRE BLVD STE 503E BEVERLY HILLS, CA 90212 |
| Engineer | Tani,, Jason Yukio; Lic. No.: C58271 | 5296 VIA PATRICIA THOUSAND OAKS, CA 91320 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/21/2021 | Partial Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 10/18/2021 | Partial Approval | JOHN KIDWELL |
| Deputy Reinf. Concrete | 10/20/2021 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 10/20/2021 | Partial Approval | JOHN KIDWELL |
| Deputy Reinf. Concrete | 10/22/2021 | Conditional Approval | DANIEL ORRANTE |
| Footing/Foundation/Slab | 11/9/2021 | No Access for Inspection | JOHN KIDWELL |
| Deputy Shotcrete | 11/10/2021 | Partial Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 11/10/2021 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2022 | Partial Approval | JOHN KIDWELL |
| Deputy Wood Construction | 1/13/2022 | Partial Approval | JOHN KIDWELL |
| Deputy Steel/Welding | 1/20/2022 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2022 | Not Ready for Inspection | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2022 | Partial Approval | JOHN KIDWELL |
| Deputy Wood Construction | 1/26/2022 | Partial Approval | JOHN KIDWELL |
| Deputy Reinf. Concrete | 1/31/2022 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 1/31/2022 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 2/11/2022 | Approved | JOHN KIDWELL |
| Deputy Wood Construction | 2/23/2022 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2022 | Corrections Issued | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2022 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2022 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 4/4/2022 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 4/7/2022 | Approved | JOHN KIDWELL |
| HVAC-Rough | 4/19/2022 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 4/22/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Green Building Rough | 4/22/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 4/22/2022 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 4/26/2022 | Approved | JOHN KIDWELL |
| Green Building Rough | 4/26/2022 | Approved | JOHN KIDWELL |
| Shower Pan | 5/2/2022 | Approved | JOHN KIDWELL |
| Drywall Nailing | 5/12/2022 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 5/12/2022 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 7/25/2022 | Approved | BRENDAN LOONEY |
| Sewer | 11/29/2022 | Partial Approval | KEVIN SARGSYAN |
| Underground Mechanical | 11/29/2022 | Approved | KEVIN SARGSYAN |
| Sewer | 12/5/2022 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 6/2/2023 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Service/Power Release | 6/2/2023 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 6/2/2023 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 9/27/2023 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 9/27/2023 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/25/2023 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Final | 11/2/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 11/2/2023 | SGSOV Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 11/8/2023 | Approved | ARAM AVEDISIAN |
| Final | 11/8/2023 | OK to Issue CofO | ARAM AVEDISIAN |
| HVAC-Final | 11/8/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 11/8/2023 | Approved | ARAM AVEDISIAN |