4525 N KRAFT AVE 91602
Certificate Information: 4525 N KRAFT AVE 91602
- Application / Permit
- 21010-20000-00877
- Plan Check / Job No.
- B21VN02133
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (66'-0"x 36'-6") 2-STORY SINGLE FAMILY DWELLING WITH ATT. 2-CAR GARAGE, NFPA -13D FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 8/11/2021
- Issuing Office
- Current Status
- CofO Issued on 3/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2021 | TROY DEGUZMAN |
| Corrections Issued | 3/3/2021 | TROY DEGUZMAN |
| Quality Review Completed | 3/8/2021 | CHON CHIO KUO |
| Building Plans Picked Up | 3/9/2021 | APPLICANT |
| Applicant returned to address corrections | 6/30/2021 | TROY DEGUZMAN |
| Applicant returned to address corrections | 8/10/2021 | TROY DEGUZMAN |
| Plan Check Approved | 8/11/2021 | TROY DEGUZMAN |
| Issued | 8/11/2021 | APPLICANT |
| CofO in Progress | 2/25/2022 | THOMAS FINNILA |
| CofO Issued | 3/24/2022 | RONALD MYRICK |
| Permit Finaled | 3/24/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 3/3/2021 | JOHN TRIANTAFYLLOS |
| Permit | Cleared | 3/3/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/4/2021 | JOHN TRIANTAFYLLOS |
| ZI | Cleared | 4/12/2021 | MIGUEL GAMBOA |
| Hydrant and Access approval | Cleared | 4/23/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 6/17/2021 | MARCO SANCHEZ |
| Green Code | Cleared | 7/1/2021 | TROY DEGUZMAN |
| Permit | Cleared | 7/6/2021 | LEE GUILBEAUX |
| Trees in Parkway | Cleared | 7/28/2021 | JOHN KIM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/12/2021 | Conditional Approval | THOMAS FINNILA |
| Underground Mechanical | 8/12/2021 | Partial Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 8/13/2021 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 8/17/2021 | Conditional Approval | THOMAS FINNILA |
| Deputy Steel/Welding | 8/26/2021 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 9/22/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2021 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 9/24/2021 | Approved | THOMAS FINNILA |
| Shower Pan | 9/29/2021 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2021 | Corrections Issued | THOMAS FINNILA |
| Shower Pan | 9/30/2021 | Approved | THOMAS FINNILA |
| HVAC-Rough | 10/1/2021 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 10/4/2021 | Approved | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2021 | Partial Approval | ARAM AVEDISIAN |
| HVAC-Rough | 10/5/2021 | Approved | ARAM AVEDISIAN |
| Deputy Wood Construction | 10/6/2021 | Approved | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 10/12/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2021 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2021 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/19/2021 | Approved | THOMAS FINNILA |
| Green Building Rough | 10/19/2021 | Approved | THOMAS FINNILA |
| MERV13>=Rough | 10/19/2021 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 10/19/2021 | Approved | THOMAS FINNILA |
| Insulation | 10/22/2021 | Corrections Issued | THOMAS FINNILA |
| Drywall Nailing | 10/28/2021 | Approved | THOMAS FINNILA |
| HVAC-Final | 1/12/2022 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 1/14/2022 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 1/21/2022 | Corrections Issued | MATT KELLERMAN |
| PLUMBING-Final | 1/25/2022 | Approved | MATT KELLERMAN |
| Footing/Foundation/Slab | 1/31/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 1/31/2022 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 1/31/2022 | Approved | THOMAS FINNILA |
| Final | 2/8/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Final | 2/8/2022 | Approved | THOMAS FINNILA |
| MERV13>=Final | 2/8/2022 | Approved | THOMAS FINNILA |
| Service/Power Release | 2/8/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 2/16/2022 | OK to Issue CofO | THOMAS FINNILA |
| Service/Power Release | 2/16/2022 | Approved | THOMAS FINNILA |