6618 N FIGUEROA ST 90042
Certificate Information: 6618 N FIGUEROA ST 90042
- Application / Permit
- 21010-20000-00874
- Plan Check / Job No.
- B21VN02128
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (27'-3 1/2"x 24'-7"),676 SQFT TWO STORY SINGLE FAMILY DWELLING WITH ATT. ONE CAR GARAGE (119 SQFT). NFPA-13D FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 1/31/2023
- Issuing Office
- Metro
- Current Status
- Issued on 1/31/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | TROY DEGUZMAN |
| Corrections Issued | 3/17/2021 | TROY DEGUZMAN |
| Quality Review Completed | 3/31/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 8/10/2022 | TROY DEGUZMAN |
| Plan Check Approved | 10/31/2022 | PETER MOSESIAN |
| Issued | 1/31/2023 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 6/2/2021 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 7/23/2021 | MATTHEW CRAIG |
| Address approval | Cleared | 11/5/2021 | JEANETTE VONG |
| BHO/Hillside ordinance | Cleared | 11/5/2021 | JEANETTE VONG |
| BHO/Hillside ordinance | Cleared | 11/5/2021 | JEANETTE VONG |
| BHO/Hillside ordinance | Cleared | 11/5/2021 | JEANETTE VONG |
| BHO/Hillside ordinance | Cleared | 11/5/2021 | JEANETTE VONG |
| BHO/Hillside ordinance | Cleared | 11/5/2021 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2021 | JEANETTE VONG |
| Highway dedication | Cleared | 11/5/2021 | JEANETTE VONG |
| Permit | Cleared | 11/5/2021 | JEANETTE VONG |
| Trees in Parkway | Cleared | 12/9/2021 | ADALBERTO VERA |
| Frnt yard landscape/Water mgmt | Cleared | 1/11/2022 | MAYELA VILLA |
| Low Impact Development | Cleared | 3/29/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 3/30/2022 | JEANETTE VONG |
| Driveway location | Cleared | 8/10/2022 | MOHAMMAD HASAN |
| Grading Pre-Inspection | Cleared | 8/10/2022 | ROBERT HUGHES |
| Green Code | Cleared | 8/10/2022 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/31/2023 | Partial Approval | AMY COLIN |
| Excavation/Setback/Form/Re-Bar | 9/8/2023 | Corrections Issued | AMY COLIN |
| Excavation/Setback/Form/Re-Bar | 9/14/2023 | Partial Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2023 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Deputy Wood Construction | 2/8/2024 | Conditional Approval | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2024 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 3/4/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 3/13/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 3/13/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 3/13/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 3/13/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 3/13/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 3/13/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 3/13/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 3/18/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 3/18/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 3/27/2024 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 3/27/2024 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 3/28/2024 | Approved | ALIZAH MAYAGOITIA |
| Wood Frame | 3/28/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/1/2024 | Corrections Issued | OSVALDO PARAMO |
| Green Building Rough | 4/1/2024 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 4/1/2024 | Approved | OSVALDO PARAMO |
| Wood Frame | 4/1/2024 | Conditional Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 4/2/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 4/2/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Wood Frame | 4/2/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Insulation | 4/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 4/9/2024 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 4/16/2024 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 4/16/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 4/23/2024 | Approved | ALIZAH MAYAGOITIA |
| Gas Test | 7/1/2024 | Approved | ALIZAH MAYAGOITIA |
| Sewer | 7/1/2024 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 7/1/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Underground Mechanical | 7/12/2024 | Partial Approval | ALIZAH MAYAGOITIA |