12271 N SARAZEN PL 91344

Certificate Information: 12271 N SARAZEN PL 91344

Application / Permit
21010-20000-00850
Plan Check / Job No.
B21VN02038
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW DETACHED RECREATION ROOM. ALL WORK PER WFPP.
Permit Issued
Issued on 6/25/2021
Issuing Office
Current Status
CofO Issued on 8/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/19/2021 APPLICANT
Assigned to Plan Check Engineer 3/8/2021 RICHARD GARCIA
Corrections Issued 3/12/2021 RICHARD GARCIA
Applicant returned to address corrections 6/9/2021 OMAR GARNICA
Building Plans Picked Up 6/21/2021 APPLICANT
Plan Check Approved 6/25/2021 OMAR GARNICA
Issued 6/25/2021 APPLICANT
CofO in Progress 6/29/2022 JAVIER RAMOS JR
Permit Finaled 8/30/2022 DANIEL ORRANTE
CofO Issued 8/30/2022 DANIEL ORRANTE
Permit Finaled 8/30/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/18/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 3/18/2021 LEE GUILBEAUX
Grading Pre-Inspection Cleared 6/9/2021 OMAR GARNICA
ZI Cleared 6/15/2021 STEVEN WECHSLER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/30/2021 Approved MARK JOHNSON
Underground Mechanical 6/30/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 7/22/2021 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Rough 7/22/2021 Not Ready for Inspection MARK JOHNSON
Green Building Rough 7/22/2021 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 7/22/2021 Corrections Issued MARK JOHNSON
Verify Sprinkler Sign Off 7/22/2021 Approved MARK JOHNSON
Wood Frame 7/22/2021 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 8/4/2021 Approved MATTHEW NELSON
ELECTRICAL-Rough 8/4/2021 Approved MATTHEW NELSON
Green Building Rough 8/4/2021 Approved MATTHEW NELSON
HVAC-Rough 8/4/2021 Approved MATTHEW NELSON
PLUMBING-Rough 8/4/2021 Approved MATTHEW NELSON
BUILDING-Rough-Frame 8/13/2021 Corrections Issued MICHAEL TEMPLE
Interior/Exterior Lathing 8/13/2021 Partial Approval MICHAEL TEMPLE
BUILDING-Rough-Frame 9/8/2021 Approved MARK JOHNSON
Drywall Nailing 9/8/2021 Not Ready for Inspection MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 9/8/2021 Approved MARK JOHNSON
Green Building Final 9/8/2021 Approved MARK JOHNSON
Insulation 9/20/2021 Conditional Approval JUSTIN HAWLEY
Insulation 10/6/2021 Approved MARK JOHNSON
Drywall Nailing 10/13/2021 Approved JOHN HAYES
ELECTRICAL-Final 2/2/2022 Corrections Issued RAUL OLAGI
Final 2/2/2022 Corrections Issued RAUL OLAGI
HVAC-Final 2/2/2022 Corrections Issued RAUL OLAGI
PLUMBING-Final 2/2/2022 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 2/2/2022 SGSOV Approved RAUL OLAGI
Smoke Detectors 2/2/2022 Approved RAUL OLAGI
ELECTRICAL-Final 2/23/2022 Approved MICHAEL TEMPLE
Final 2/23/2022 Not Ready for Inspection MICHAEL TEMPLE
Pre-Inspection 2/28/2022 Corrections Issued MICHAEL TEMPLE
Final 6/28/2022 OK to Issue CofO JAVIER RAMOS JR
Service/Power Release 6/28/2022 Approved JAVIER RAMOS JR