135 W 42ND PL 90037

Certificate Information: 135 W 42ND PL 90037

Application / Permit
21010-20000-00817
Plan Check / Job No.
B21VN01959
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD (35'-0"x 19'-0") ACCESSORY DWELLING UNIT PER GCS 65852.2 (e) (1) (B) and LAMC 12.22 A.33 (c), (d) and (g).WORK PER LA STD WFPP.
Permit Issued
Issued on 9/27/2021
Issuing Office
Current Status
CofO Corrected on 10/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2021 APPLICANT
Assigned to Plan Check Engineer 3/8/2021 DAVID CASTILLO
Corrections Issued 3/15/2021 DAVID CASTILLO
Plan Check Approved 9/27/2021 TROY DEGUZMAN
Issued 9/27/2021 APPLICANT
Building Plans Picked Up 9/27/2021 APPLICANT
CofO in Progress 7/15/2022 JOAQUIN GREENOUGH
CofO Issued-Status Void 8/26/2022 DEROLD HAUFF
Permit Finaled-Status Void 8/26/2022 DEROLD HAUFF
Re-Activate Permit 10/17/2022 DEROLD HAUFF
Permit Finaled 10/21/2022 DEROLD HAUFF
CofO Corrected 10/21/2022 DEROLD HAUFF
Permit Finaled 10/21/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/14/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/14/2021 JEANIE LAM
Sewer availability Cleared 4/14/2021 JEANIE LAM
Low Impact Development Cleared 8/3/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 8/3/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/2/2021 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Barrier 11/2/2021 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Subgrade 11/2/2021 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 11/8/2021 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Barrier 11/8/2021 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Subgrade 11/8/2021 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 11/15/2021 Approved JOAQUIN GREENOUGH
METHANE-Barrier 11/15/2021 Approved JOAQUIN GREENOUGH
METHANE-Rough 11/15/2021 Approved JOAQUIN GREENOUGH
METHANE-Subgrade 11/15/2021 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 12/1/2021 Approved FREDDIE RIVERA
Green Building Rough 12/1/2021 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 12/17/2021 Corrections Issued LILIANA PORTILLO
Gas Test 12/17/2021 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 12/17/2021 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 12/17/2021 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 12/21/2021 Approved JOAQUIN GREENOUGH
Gas Test 12/21/2021 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 12/21/2021 Approved JOAQUIN GREENOUGH
Rough-Elec/Plmb/HVAC 12/21/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Sewer 12/29/2021 Corrections Issued ALEJANDRO DE ARTOLA
Shower Pan 12/29/2021 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/30/2021 Approved SABAS ALONSO
Green Building Rough 12/30/2021 Approved SABAS ALONSO
HVAC-Rough 12/30/2021 Approved SABAS ALONSO
Sewer 12/30/2021 Approved SABAS ALONSO
Insulation 1/6/2022 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 1/6/2022 Partial Approval JOAQUIN GREENOUGH
Drywall Nailing 1/11/2022 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 1/26/2022 Approved JOAQUIN GREENOUGH
Final 3/24/2022 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 3/24/2022 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 3/24/2022 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 3/24/2022 No Access for Inspection JOAQUIN GREENOUGH
Final 5/11/2022 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 5/11/2022 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 5/11/2022 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 5/11/2022 Corrections Issued JOAQUIN GREENOUGH
Final 5/26/2022 Conditional Approval HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 5/26/2022 SGSOV Approved HORACE FULTZ
Smoke Detectors 5/26/2022 Approved HORACE FULTZ
ELECTRICAL-Final 6/8/2022 Approved HORACE FULTZ
HVAC-Final 6/8/2022 Approved HORACE FULTZ
MERV13>=Final 6/8/2022 Approved HORACE FULTZ
PLUMBING-Final 6/8/2022 Approved HORACE FULTZ
Service/Power Release 6/8/2022 Approved HORACE FULTZ
Final 7/13/2022 OK to Issue CofO JOAQUIN GREENOUGH
Final 8/22/2022 Partial Inspection JOAQUIN GREENOUGH