135 W 42ND PL 90037
Certificate Information: 135 W 42ND PL 90037
- Application / Permit
- 21010-20000-00817
- Plan Check / Job No.
- B21VN01959
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD (35'-0"x 19'-0") ACCESSORY DWELLING UNIT PER GCS 65852.2 (e) (1) (B) and LAMC 12.22 A.33 (c), (d) and (g).WORK PER LA STD WFPP.
- Permit Issued
- Issued on 9/27/2021
- Issuing Office
- Current Status
- CofO Corrected on 10/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2021 | DAVID CASTILLO |
| Corrections Issued | 3/15/2021 | DAVID CASTILLO |
| Plan Check Approved | 9/27/2021 | TROY DEGUZMAN |
| Issued | 9/27/2021 | APPLICANT |
| Building Plans Picked Up | 9/27/2021 | APPLICANT |
| CofO in Progress | 7/15/2022 | JOAQUIN GREENOUGH |
| CofO Issued-Status Void | 8/26/2022 | DEROLD HAUFF |
| Permit Finaled-Status Void | 8/26/2022 | DEROLD HAUFF |
| Re-Activate Permit | 10/17/2022 | DEROLD HAUFF |
| Permit Finaled | 10/21/2022 | DEROLD HAUFF |
| CofO Corrected | 10/21/2022 | DEROLD HAUFF |
| Permit Finaled | 10/21/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/14/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2021 | JEANIE LAM |
| Sewer availability | Cleared | 4/14/2021 | JEANIE LAM |
| Low Impact Development | Cleared | 8/3/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 8/3/2021 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/2/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Barrier | 11/2/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 11/2/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 11/8/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Barrier | 11/8/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 11/8/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 11/15/2021 | Approved | JOAQUIN GREENOUGH |
| METHANE-Barrier | 11/15/2021 | Approved | JOAQUIN GREENOUGH |
| METHANE-Rough | 11/15/2021 | Approved | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 11/15/2021 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 12/1/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 12/17/2021 | Corrections Issued | LILIANA PORTILLO |
| Gas Test | 12/17/2021 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/17/2021 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 12/17/2021 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 12/21/2021 | Approved | JOAQUIN GREENOUGH |
| Gas Test | 12/21/2021 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 12/21/2021 | Approved | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 12/21/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Sewer | 12/29/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Shower Pan | 12/29/2021 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/30/2021 | Approved | SABAS ALONSO |
| Green Building Rough | 12/30/2021 | Approved | SABAS ALONSO |
| HVAC-Rough | 12/30/2021 | Approved | SABAS ALONSO |
| Sewer | 12/30/2021 | Approved | SABAS ALONSO |
| Insulation | 1/6/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 1/6/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Drywall Nailing | 1/11/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 1/26/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 3/24/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 3/24/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 3/24/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 3/24/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| Final | 5/11/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 5/11/2022 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 5/11/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 5/11/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 5/26/2022 | Conditional Approval | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 5/26/2022 | SGSOV Approved | HORACE FULTZ |
| Smoke Detectors | 5/26/2022 | Approved | HORACE FULTZ |
| ELECTRICAL-Final | 6/8/2022 | Approved | HORACE FULTZ |
| HVAC-Final | 6/8/2022 | Approved | HORACE FULTZ |
| MERV13>=Final | 6/8/2022 | Approved | HORACE FULTZ |
| PLUMBING-Final | 6/8/2022 | Approved | HORACE FULTZ |
| Service/Power Release | 6/8/2022 | Approved | HORACE FULTZ |
| Final | 7/13/2022 | OK to Issue CofO | JOAQUIN GREENOUGH |
| Final | 8/22/2022 | Partial Inspection | JOAQUIN GREENOUGH |