Application / Permit
21010-20000-00764
Plan Check / Job No.
B21VN01859
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 25' X 48'-7" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)ALL WORK PER WFPP.
Permit Issued
Issued on 8/31/2021
Issuing Office
Current Status
CofO Issued on 4/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/17/2021 APPLICANT
Assigned to Plan Check Engineer 3/8/2021 ALFREDO JARA
Corrections Issued 3/15/2021 ALFREDO JARA
Applicant returned to address corrections 8/4/2021 OMAR GARNICA
Applicant returned to address corrections 8/24/2021 OMAR GARNICA
Plan Check Approved 8/31/2021 OMAR GARNICA
No Progress 8/31/2021 OMAR GARNICA
Plan Check Approved 8/31/2021 OMAR GARNICA
Issued 8/31/2021 APPLICANT
Building Plans Picked Up 8/31/2021 APPLICANT
CofO in Progress 3/14/2023 WILLIAM WREN
Permit Finaled 4/4/2023 DANIEL ORRANTE
CofO Issued 4/4/2023 DANIEL ORRANTE
Permit Finaled 4/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/22/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/22/2021 ADRIAN CASTRO
Private sewage disp. approval Cleared 4/6/2021 PATRICK MISCHLICH
Specific Plan Cleared 4/6/2021 PEGGY MALONE-BROWN
Hydrant and Access approval Cleared 5/18/2021 MATTHEW CRAIG
Low Impact Development Cleared 7/22/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 7/27/2021 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 8/23/2021 OMAR GARNICA
GPI Written Notices Cleared 8/31/2021 OMAR GARNICA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/15/2021 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 10/20/2021 Approved MATTHEW NELSON
Pre-Inspection 10/20/2021 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 11/4/2021 Partial Approval MATTHEW NELSON
PLUMBING-Rough 11/4/2021 Partial Approval MATTHEW NELSON
Pre-Inspection 11/5/2021 Corrections Issued DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 11/19/2021 Corrections Issued MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 11/23/2021 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 12/16/2021 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 12/16/2021 Corrections Issued MATTHEW NELSON
MERV13>=Rough 12/16/2021 Not Ready for Inspection MATTHEW NELSON
Verify Sprinkler Sign Off 12/16/2021 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 1/10/2022 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 1/10/2022 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 1/10/2022 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 1/10/2022 Approved MATTHEW NELSON
HVAC-Rough 1/10/2022 Not Ready for Inspection MATTHEW NELSON
MERV13>=Rough 1/10/2022 Approved MATTHEW NELSON
PLUMBING-Rough 1/10/2022 Corrections Issued MATTHEW NELSON
Verify Sprinkler Sign Off 1/10/2022 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 1/14/2022 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 1/14/2022 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 1/20/2022 Approved MATTHEW NELSON
Green Building Rough 1/20/2022 Approved MATTHEW NELSON
Insulation 1/28/2022 Approved MATTHEW NELSON
Drywall Nailing 2/11/2022 Approved MATTHEW NELSON
Shower Pan 2/11/2022 Not Ready for Inspection MATTHEW NELSON
Interior/Exterior Lathing 2/16/2022 Approved WILLIAM WREN
Shower Pan 2/16/2022 Not Ready for Inspection WILLIAM WREN
Interior/Exterior Lathing 2/25/2022 Approved MATTHEW NELSON
Shower Pan 2/25/2022 Approved MATTHEW NELSON
Final 10/26/2022 Not Ready for Inspection MATTHEW NELSON
Green Building Final 10/26/2022 Not Ready for Inspection MATTHEW NELSON
MERV13>=Final 10/26/2022 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/26/2022 SGSOV Not Ready MATTHEW NELSON
Service/Power Release 10/26/2022 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 10/26/2022 Not Ready for Inspection MATTHEW NELSON
Final 11/8/2022 Corrections Issued MATTHEW NELSON
Green Building Final 11/8/2022 Approved MATTHEW NELSON
MERV13>=Final 11/8/2022 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 11/8/2022 SGSOV Approved MATTHEW NELSON
Service/Power Release 11/8/2022 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 11/8/2022 Approved MATTHEW NELSON
Final 2/16/2023 Not Ready for Inspection WILLIAM WREN
Service/Power Release 2/16/2023 Not Ready for Inspection WILLIAM WREN
Final 3/2/2023 Not Ready for Inspection DAVID ANDERSON
Service/Power Release 3/2/2023 Not Ready for Inspection DAVID ANDERSON
Final 3/7/2023 Corrections Issued WILLIAM WREN
Service/Power Release 3/7/2023 Not Ready for Inspection WILLIAM WREN
Final 3/10/2023 OK to Issue CofO WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 3/10/2023 SGSOV Approved WILLIAM WREN
Service/Power Release 3/10/2023 Approved WILLIAM WREN