16729 W ADDISON ST 91436
Certificate Information: 16729 W ADDISON ST 91436
- Application / Permit
- 21010-20000-00712
- Plan Check / Job No.
- B21VN01740
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 22'-0" X 28'-0" ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g). SPRINKLERED THRU-OUT.
- Permit Issued
- Issued on 7/30/2021
- Issuing Office
- Current Status
- CofO Issued on 4/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2021 | ARTIN ZARUKIAN |
| Corrections Issued | 3/6/2021 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 3/9/2021 | APPLICANT |
| Plan Check Approved | 7/28/2021 | ARTIN ZARUKIAN |
| Issued | 7/30/2021 | APPLICANT |
| CofO in Progress | 4/26/2022 | DAVID SANDOVAL |
| Permit Finaled | 4/29/2022 | MICHAEL SMITH |
| CofO Issued | 4/29/2022 | MICHAEL SMITH |
| Permit Finaled | 4/29/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/22/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 4/27/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 7/6/2021 | ORVAL HERNANDEZ-MARCI |
| Address approval | Cleared | 7/8/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 7/8/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/12/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/12/2021 | Approved | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2021 | Partial Approval | RONALD COWAN |
| Green Building Rough | 8/27/2021 | Not Ready for Inspection | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2021 | Approved | RONALD COWAN |
| HVAC-Rough | 10/13/2021 | Approved | RONALD COWAN |
| ELECTRICAL-Rough | 10/21/2021 | No Access for Inspection | VINCENT HANLEY |
| Shower Pan | 10/25/2021 | Approved | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 10/29/2021 | No Access for Inspection | DAVID SANDOVAL |
| Green Building Rough | 10/29/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 10/29/2021 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 11/3/2021 | Approved | RONALD COWAN |
| Green Building Rough | 11/3/2021 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 11/3/2021 | Approved | RONALD COWAN |
| Insulation | 11/8/2021 | Approved | RONALD COWAN |
| Drywall Nailing | 11/12/2021 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 3/23/2022 | Corrections Issued | DAVID SANDOVAL |
| HVAC-Final | 3/23/2022 | Corrections Issued | DAVID SANDOVAL |
| ELECTRICAL-Final | 4/1/2022 | Approved | DAVID SANDOVAL |
| HVAC-Final | 4/1/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Final | 4/1/2022 | Approved | DAVID SANDOVAL |
| Final | 4/25/2022 | OK to Issue CofO | DAVID SANDOVAL |
| Footing/Foundation/Slab | 4/25/2022 | Approved | DAVID SANDOVAL |
| Green Building Final | 4/25/2022 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 4/25/2022 | SGSOV Approved | DAVID SANDOVAL |
| Service/Power Release | 4/25/2022 | Approved | DAVID SANDOVAL |
| Smoke Detectors | 4/25/2022 | Approved | DAVID SANDOVAL |