4508 N HASKELL AVE 91436

Certificate Information: 4508 N HASKELL AVE 91436

Application / Permit
21010-20000-00678
Plan Check / Job No.
B21VN01643
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
(N) 1-STORY DETACHED CABANA
Permit Issued
Issued on 9/16/2021
Issuing Office
Valley
Current Status
CofO Issued on 11/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 NILOOFAR MEHRAIN
Corrections Issued 3/16/2021 NILOOFAR MEHRAIN
Quality Review Completed 3/16/2021 CHON CHIO KUO
Building Plans Picked Up 3/16/2021 APPLICANT
Applicant returned to address corrections 5/7/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/10/2021 NILOOFAR MEHRAIN
Plan Check Approved 8/16/2021 NILOOFAR MEHRAIN
Issued 9/16/2021 APPLICANT
CofO in Progress 11/14/2022 SEAN WIRCH
CofO Issued 11/14/2022 JOHN JANSON
Permit Finaled 11/14/2022 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/19/2021 ADRIAN CASTRO
Low Impact Development Cleared 7/19/2021 MARCO SANCHEZ
GPI Written Notices Cleared 8/3/2021 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 8/3/2021 NILOOFAR MEHRAIN
Roof/Waste drainage to street Cleared 8/3/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/1/2021 Approved DAVID SANDOVAL
Footing/Foundation/Slab 12/1/2021 Partial Approval DAVID SANDOVAL
Footing/Foundation/Slab 12/20/2021 Approved DAVID SANDOVAL
Deputy Reinf. Concrete 12/22/2021 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/30/2022 Approved DAVID SANDOVAL
ELECTRICAL-Rough 4/4/2022 Approved DAVID SANDOVAL
Gas Test 4/4/2022 Partial Approval DAVID SANDOVAL
PLUMBING-Rough 4/4/2022 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 4/7/2022 Not Ready for Inspection DAVID SCANTLIN
Verify Sprinkler Sign Off 4/7/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 4/13/2022 Approved DAVID SCANTLIN
Deck 4/21/2022 Not Ready for Inspection SEAN HAUPT
Insulation 4/21/2022 Not Ready for Inspection SEAN HAUPT
Interior/Exterior Lathing 4/21/2022 Approved SEAN HAUPT
Insulation 4/26/2022 Approved MORRIS JACKSON
ELECTRICAL-Final 10/3/2022 Approved VINCENT HANLEY
Final 10/3/2022 Corrections Issued VINCENT HANLEY
Insulation 10/3/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 10/3/2022 SGSOV Approved VINCENT HANLEY
Service/Power Release 10/3/2022 Approved VINCENT HANLEY
Smoke Detectors 10/3/2022 Approved VINCENT HANLEY
Final 11/15/2022 OK to Issue CofO SEAN WIRCH