4508 N HASKELL AVE 91436

Certificate Information: 4508 N HASKELL AVE 91436

Application / Permit
21010-20000-00676
Plan Check / Job No.
B21VN01643
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED 3-CAR GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 9/16/2021
Issuing Office
Valley
Current Status
CofO Issued on 11/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 NILOOFAR MEHRAIN
Corrections Issued 3/16/2021 NILOOFAR MEHRAIN
Quality Review Completed 3/16/2021 CHON CHIO KUO
Building Plans Picked Up 3/16/2021 APPLICANT
Applicant returned to address corrections 5/7/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/10/2021 NILOOFAR MEHRAIN
Plan Check Approved 8/16/2021 NILOOFAR MEHRAIN
Issued 9/16/2021 APPLICANT
CofO in Progress 11/10/2022 SEAN WIRCH
Permit Finaled 11/10/2022 JOHN JANSON
CofO Issued 11/10/2022 JOHN JANSON
Permit Finaled 11/10/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/22/2021 ADRIAN CASTRO
Permit Cleared 3/22/2021 ADRIAN CASTRO
Sewer availability Cleared 5/11/2021 ADRIAN CASTRO
Trees in Parkway Cleared 6/10/2021 JOHN KIM
Low Impact Development Cleared 7/19/2021 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 7/31/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/3/2021 CARLOS AGUILERA
GPI Written Notices Cleared 8/3/2021 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 8/3/2021 NILOOFAR MEHRAIN
Hydrant and Access approval Cleared 8/4/2021 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/12/2021 Approved JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 12/1/2021 Approved DAVID SANDOVAL
Footing/Foundation/Slab 12/1/2021 Approved DAVID SANDOVAL
Deputy Seismic Resistance 12/3/2021 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 1/31/2022 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/7/2022 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/22/2022 Approved DAVID SANDOVAL
HVAC-Rough 3/22/2022 Approved DAVID SANDOVAL
ELECTRICAL-Rough 4/4/2022 Approved DAVID SANDOVAL
Gas Test 4/4/2022 Partial Approval DAVID SANDOVAL
Green Building Rough 4/4/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 4/4/2022 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 4/7/2022 Not Ready for Inspection DAVID SCANTLIN
Shower Pan 4/7/2022 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 4/7/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 4/13/2022 Approved DAVID SCANTLIN
Green Building Rough 4/13/2022 Approved DAVID SCANTLIN
Interior/Exterior Lathing 4/21/2022 Approved SEAN HAUPT
Insulation 4/26/2022 Approved MORRIS JACKSON
Drywall Nailing 5/4/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 5/4/2022 Approved DAVID SANDOVAL
Gas Test 8/22/2022 Approved PETER FOLLING
ELECTRICAL-Final 10/3/2022 Approved VINCENT HANLEY
Green Building Final 10/3/2022 Approved VINCENT HANLEY
HVAC-Final 10/3/2022 Approved VINCENT HANLEY
PLUMBING-Final 10/3/2022 Approved VINCENT HANLEY
Service/Power Release 10/3/2022 Approved VINCENT HANLEY
Smoke Detectors 10/3/2022 Approved VINCENT HANLEY
Final 10/7/2022 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 10/7/2022 SGSOV Approved VINCENT HANLEY
Final 11/14/2022 OK to Issue CofO SEAN WIRCH