10400 N HILLHAVEN AVE 91042
Certificate Information: 10400 N HILLHAVEN AVE 91042
- Application / Permit
- 21010-20000-00641
- Plan Check / Job No.
- B21VN01578
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- NEW 44' X 14'-6" FULLY SPRINKLERED DETACHED ACCESSORY LIVING QUARTERS PER ENGINEER
- Permit Issued
- Issued on 3/23/2022
- Issuing Office
- Current Status
- CofO Issued on 10/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 3/2/2021 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 2/20/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 3/4/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/17/2022 | APPLICANT |
| Issued | 3/23/2022 | APPLICANT |
| CofO in Progress | 10/8/2025 | WILLIAM WREN |
| CofO Issued | 10/16/2025 | RUBEN SALAS |
| Permit Finaled | 10/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Specific Plan | Cleared | 9/23/2021 | STEVEN WECHSLER |
| Low Impact Development | Cleared | 9/28/2021 | JORGE MEJIA LEMUS |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2021 | AMIR KASHFI |
| Sewer availability | Cleared | 11/17/2021 | AMIR KASHFI |
| Hydrant and Access approval | Cleared | 1/24/2022 | GILBERT URREA |
| GPI Written Notices | Cleared | 2/22/2022 | JEROME MAGAT PALMA |
| Grading Pre-Inspection | Cleared | 2/22/2022 | JEROME MAGAT PALMA |
| Roof/Waste drainage to street | Cleared | 2/24/2022 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Li,, Dacheng David; Lic. No.: C58075 | 1400 N KRAEMER BLVD #712 PLACENTIA, CA 92781 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/9/2022 | Partial Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 10/17/2022 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 10/17/2022 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 11/30/2022 | Partial Approval | WILLIAM WREN |
| Footing/Foundation/Slab | 12/5/2022 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2023 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 3/14/2023 | Not Ready for Inspection | WILLIAM WREN |
| HVAC-Rough | 3/14/2023 | Not Ready for Inspection | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2023 | Approved | WILLIAM WREN |
| Deputy Wood Construction | 3/17/2023 | Conditional Approval | MICHAEL SMITH |
| Interior/Exterior Lathing | 4/17/2023 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 4/25/2023 | Approved | WILLIAM WREN |
| Sewer | 4/25/2023 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 5/1/2023 | Not Ready for Inspection | WILLIAM WREN |
| Underground Mechanical | 6/6/2023 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 11/6/2023 | Approved | WILLIAM WREN |
| HVAC-Rough | 11/6/2023 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 11/6/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 11/13/2023 | Approved | WILLIAM WREN |
| Green Building Rough | 11/13/2023 | Approved | WILLIAM WREN |
| Verify Sprinkler Sign Off | 11/13/2023 | Approved | WILLIAM WREN |
| Insulation | 11/30/2023 | Partial Approval | MATTHEW NELSON |
| Drywall Nailing | 12/11/2023 | Approved | WILLIAM WREN |
| Shower Pan | 12/20/2023 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 12/29/2023 | Approved | WILLIAM WREN |
| Final | 4/17/2025 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 4/17/2025 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 4/17/2025 | SGSOV Approved | WILLIAM WREN |
| Service/Power Release | 4/17/2025 | Approved | WILLIAM WREN |
| Smoke Detectors | 4/17/2025 | Approved | WILLIAM WREN |
| Final | 5/23/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Final | 8/19/2025 | OK to Issue CofO | WILLIAM WREN |