13142 W DAVENTRY ST 91331
Certificate Information: 13142 W DAVENTRY ST 91331
- Application / Permit
- 21010-20000-00617
- Plan Check / Job No.
- B21VN01536
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 24' X 40' DETACHED 1-STORY ACCESSORY DWELLING UNIT WITH ATTACHED 4' X 4' 6" COVERED PORCH PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 5/16/2022
- Issuing Office
- Current Status
- Issued on 5/16/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 2/27/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 2/19/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 5/15/2022 | GURUNATH NESARAJAH |
| Issued | 5/16/2022 | APPLICANT |
| Building Plans Picked Up | 5/18/2022 | APPLICANT |
Permit Application Clearance Information
| ZI | Cleared | 4/6/2021 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 5/26/2021 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 7/16/2021 | RIDWAN HARDY |
| Address approval | Cleared | 8/10/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 12/3/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 2/2/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/7/2022 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/4/2022 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 10/27/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/4/2022 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 11/4/2022 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 1/20/2023 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2023 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 1/25/2023 | Conditional Approval | ROBERT GOLD |
| Green Building Rough | 1/25/2023 | Not Ready for Inspection | ROBERT GOLD |
| HVAC-Rough | 1/25/2023 | Not Ready for Inspection | ROBERT GOLD |
| MERV13>=Rough | 1/25/2023 | Corrections Issued | ROBERT GOLD |
| PLUMBING-Rough | 1/25/2023 | Partial Inspection | ROBERT GOLD |
| Shower Pan | 1/25/2023 | Corrections Issued | ROBERT GOLD |
| Verify Sprinkler Sign Off | 1/25/2023 | Not Ready for Inspection | ROBERT GOLD |
| Insulation | 2/14/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/14/2023 | Approved | MICHEL ABAJAN |
| Shower Pan | 2/14/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 2/22/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/22/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/6/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 6/6/2023 | Approved | MICHEL ABAJAN |
| Final | 6/6/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 6/6/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 6/6/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 6/6/2023 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 6/6/2023 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 6/6/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 6/6/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 6/6/2023 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 6/6/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 6/6/2023 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 7/27/2023 | Partial Inspection | MICHEL ABAJAN |
| Sewer | 7/27/2023 | Partial Inspection | MICHEL ABAJAN |