7343 N ETIWANDA AVE 91335
Certificate Information: 7343 N ETIWANDA AVE 91335
- Application / Permit
- 21010-20000-00616
- Plan Check / Job No.
- B21VN01530
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 17'-8" X 30'-9" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK PER WFPP. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
- Permit Issued
- Issued on 3/1/2022
- Issuing Office
- Current Status
- CofO Issued on 5/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/26/2021 | PARISA ZAHABI |
| Corrections Issued | 3/3/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 11/4/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 1/7/2022 | ROSENDO MEDINA |
| Plan Check Approved | 3/1/2022 | ROSENDO MEDINA |
| Issued | 3/1/2022 | APPLICANT |
| Building Plans Picked Up | 3/2/2022 | APPLICANT |
| CofO in Progress | 4/3/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 5/2/2025 | JOHN JANSON |
| CofO Issued | 5/2/2025 | JOHN JANSON |
| Permit Finaled | 5/2/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/19/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 3/19/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/19/2021 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 5/1/2021 | JOHN CONNEALLY |
| Roof/Waste drainage to street | Cleared | 3/1/2022 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 3/1/2022 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/12/2024 | Partial Approval | JEFFREY BULL |
| Excavation/Setback/Form/Re-Bar | 3/19/2024 | Approved | JEFFREY BULL |
| Footing/Foundation/Slab | 3/19/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 3/29/2024 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 3/29/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 3/29/2024 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 4/30/2024 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Rough | 4/30/2024 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 4/30/2024 | Not Ready for Inspection | JEFFREY BULL |
| HVAC-Rough | 4/30/2024 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 4/30/2024 | Approved | JEFFREY BULL |
| Sewer | 4/30/2024 | Approved | JEFFREY BULL |
| Underground Mechanical | 4/30/2024 | Partial Approval | JEFFREY BULL |
| Verify Sprinkler Sign Off | 4/30/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 5/21/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 5/21/2024 | Approved | JEFFREY BULL |
| Gas Test | 5/21/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 5/21/2024 | Approved | JEFFREY BULL |
| HVAC-Rough | 5/21/2024 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 5/21/2024 | Partial Approval | JEFFREY BULL |
| PLUMBING-Rough | 5/21/2024 | Approved | JEFFREY BULL |
| Rough-Elec/Plmb/HVAC | 5/21/2024 | Approved | JEFFREY BULL |
| Insulation | 6/4/2024 | Approved | JEFFREY BULL |
| Drywall Nailing | 6/10/2024 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 6/10/2024 | Approved | HENRY KIM |
| ELECTRICAL-Final | 9/16/2024 | Approved | JEFFREY BULL |
| Final | 9/16/2024 | Corrections Issued | JEFFREY BULL |
| HVAC-Final | 9/16/2024 | Approved | JEFFREY BULL |
| PLUMBING-Final | 9/16/2024 | Approved | JEFFREY BULL |
| Final | 3/19/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 3/19/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 3/19/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 3/19/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 3/19/2025 | Approved | ARUTYUN MADATYAN |
| Final | 4/3/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| Service/Power Release | 4/3/2025 | Approved | ARUTYUN MADATYAN |