7343 N ETIWANDA AVE 91335

Certificate Information: 7343 N ETIWANDA AVE 91335

Application / Permit
21010-20000-00616
Plan Check / Job No.
B21VN01530
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 17'-8" X 30'-9" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK PER WFPP. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 3/1/2022
Issuing Office
Current Status
CofO Issued on 5/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/9/2021 APPLICANT
Assigned to Plan Check Engineer 2/26/2021 PARISA ZAHABI
Corrections Issued 3/3/2021 PARISA ZAHABI
Applicant returned to address corrections 11/4/2021 PARISA ZAHABI
Applicant returned to address corrections 1/7/2022 ROSENDO MEDINA
Plan Check Approved 3/1/2022 ROSENDO MEDINA
Issued 3/1/2022 APPLICANT
Building Plans Picked Up 3/2/2022 APPLICANT
CofO in Progress 4/3/2025 ARUTYUN MADATYAN
Permit Finaled 5/2/2025 JOHN JANSON
CofO Issued 5/2/2025 JOHN JANSON
Permit Finaled 5/2/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/19/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/19/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/19/2021 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 5/1/2021 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 3/1/2022 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 3/1/2022 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/12/2024 Partial Approval JEFFREY BULL
Excavation/Setback/Form/Re-Bar 3/19/2024 Approved JEFFREY BULL
Footing/Foundation/Slab 3/19/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 3/29/2024 Partial Approval JOHN KIDWELL
Green Building Rough 3/29/2024 Not Ready for Inspection JOHN KIDWELL
Verify Sprinkler Sign Off 3/29/2024 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 4/30/2024 Not Ready for Inspection JEFFREY BULL
ELECTRICAL-Rough 4/30/2024 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 4/30/2024 Approved JEFFREY BULL
Green Building Rough 4/30/2024 Not Ready for Inspection JEFFREY BULL
HVAC-Rough 4/30/2024 Approved JEFFREY BULL
PLUMBING-Rough 4/30/2024 Approved JEFFREY BULL
Sewer 4/30/2024 Approved JEFFREY BULL
Underground Mechanical 4/30/2024 Partial Approval JEFFREY BULL
Verify Sprinkler Sign Off 4/30/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 5/21/2024 Approved JEFFREY BULL
ELECTRICAL-Rough 5/21/2024 Approved JEFFREY BULL
Gas Test 5/21/2024 Approved JEFFREY BULL
Green Building Rough 5/21/2024 Approved JEFFREY BULL
HVAC-Rough 5/21/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 5/21/2024 Partial Approval JEFFREY BULL
PLUMBING-Rough 5/21/2024 Approved JEFFREY BULL
Rough-Elec/Plmb/HVAC 5/21/2024 Approved JEFFREY BULL
Insulation 6/4/2024 Approved JEFFREY BULL
Drywall Nailing 6/10/2024 Approved HENRY KIM
Interior/Exterior Lathing 6/10/2024 Approved HENRY KIM
ELECTRICAL-Final 9/16/2024 Approved JEFFREY BULL
Final 9/16/2024 Corrections Issued JEFFREY BULL
HVAC-Final 9/16/2024 Approved JEFFREY BULL
PLUMBING-Final 9/16/2024 Approved JEFFREY BULL
Final 3/19/2025 Corrections Issued ARUTYUN MADATYAN
Green Building Final 3/19/2025 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 3/19/2025 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 3/19/2025 Not Ready for Inspection ARUTYUN MADATYAN
Smoke Detectors 3/19/2025 Approved ARUTYUN MADATYAN
Final 4/3/2025 OK to Issue CofO ARUTYUN MADATYAN
Service/Power Release 4/3/2025 Approved ARUTYUN MADATYAN